Hi Vince,

thanks! haha but my contractor is quite insistent that i use 600X600 for homo tiles because of the potential worry of uneven-ness..he said my house is granite hence the thickness and the weight of the tiles can hold it down...

he also recommend me to use parquet instead of laminates..

(he is the contractor who did my current house and he is a family friend, have yet to see the final quote) but he told me it would be 15-17k depend on my final requirement.

just to share my granite flooring if any neighbour are interested! :yamseng:

PB051600.jpg

PB041597.jpg

that's nice, your contractor recommend you & give advise. good...

can pm me your contractor , i'm interested to find more ... fionacll@hotmail.com thanks

 

Share this post


Link to post
Share on other sites

Join 46,923 satisfied homeowners who used renotalk quotation service to find interior designers. Get an estimated quotation

BLK 25b........not ready!:yamseng:!

f_IMG8595m_c774d20.jpg

f_IMG8596m_e51196b.jpg

ok, this is the broken window pane...

f_BrokenWindom_69c5b2e.jpg

f_BrokenWindom_3aabde0.jpg

What???

Broken window panel?

How come the inspector can give it a pass?

Aiyo, for me, I think better ask someone here who got the sharp eye...me, sotong eye...sometime cannot see also....even my friend walk pass me, I also cannot see them...hehehe

 

Share this post


Link to post
Share on other sites
that's nice, your contractor recommend you & give advise. good...

can pm me your contractor , i'm interested to find more ... fionacll@hotmail.com thanks

hi gal, you have mail.

i guess for me, his after-service is proven to be good and dependable.

happy, i just remem when we got the brochure from HDB, there is only 1 missing unit in block 25B for balloting...you are the only one from SER to choose block 25B?

 

Share this post


Link to post
Share on other sites
ok, this is the broken window pane...

f_BrokenWindom_69c5b2e.jpg

f_BrokenWindom_3aabde0.jpg

WOW!:yamseng: U really broke a big piece leh. Was still thinking it's like the window frame kind. Haa.. good job.

How's your renov getting on anyway? Mine's doing chemical wash today. Carpenter has taken necessary measurement. So my cabinets n wardrobe should be up by another 2 to 3 wks.

Can i check have you inform HDB on the date to surrender the current flat? I am thinking of extending to a later date. Dun wish to move in so soon... as so many flats have yet to undergo their renov yet. I heard we can extend by another month. Any idea?

 

Share this post


Link to post
Share on other sites
hi gal, you have mail.

i guess for me, his after-service is proven to be good and dependable.

happy, i just remem when we got the brochure from HDB, there is only 1 missing unit in block 25B for balloting...you are the only one from SER to choose block 25B?

Hi LIN

Yes, I am from sers.

I remembered even after I choose my units and deadline is closed, there are still many units left @ blk 25b.

Ur...what is 'only 1 missing unit in blk 25b?'

 

Share this post


Link to post
Share on other sites

hehe they listed all the units available for balloting for us, if i didnt reme wrongly only 23-118 of 25B is missing from the list which i presume is yours? or is it 22 or 21...haha

 

Share this post


Link to post
Share on other sites
hehe they listed all the units available for balloting for us, if i didnt reme wrongly only 23-118 of 25B is missing from the list which i presume is yours? or is it 22 or 21...haha

Oh icic..hahaha...dont know what happen to my brain...sometimes, act very slow.. no lah, not my unit, not 23rd floor lah.

 

Share this post


Link to post
Share on other sites
WOW!:) U really broke a big piece leh. Was still thinking it's like the window frame kind. Haa.. good job.

How's your renov getting on anyway? Mine's doing chemical wash today. Carpenter has taken necessary measurement. So my cabinets n wardrobe should be up by another 2 to 3 wks.

Can i check have you inform HDB on the date to surrender the current flat? I am thinking of extending to a later date. Dun wish to move in so soon... as so many flats have yet to undergo their renov yet. I heard we can extend by another month. Any idea?

ya, broke a big piece so that the cheaper tobshiba invert unit can go thru'... :yamseng:

think mine will finish in early dec. i'm really taking my own sweet time. reno works will stop for this week coz my dad went hong kong for a tour. hahah :curse: living room tiles should complete next week. Kitchen cabinet/wardrobe probably end of nov.

btw, i'm not from sers. i got the flat from balloting... :curse:

What???

Broken window panel?

How come the inspector can give it a pass?

Aiyo, for me, I think better ask someone here who got the sharp eye...me, sotong eye...sometime cannot see also....even my friend walk pass me, I also cannot see them...hehehe

no lah, i broke it on purpose so that i can fit the bigger toshiba invertor unit onto the aircon ledge. :curse:

coz buying the smaller mitshibishi invertor unit will cost about $700 more. Replacing the broken window pane cost only about $220. :curse:

 

Share this post


Link to post
Share on other sites

Hi all,

We collected our keys last sat, went in and check, there is like no defects with the exceptions of the electrical sockets, nearly all of them are faulty..

Can I also ask will HDB replace the windows if they are rusty?? I have one handle which is rusty liao..

 

Share this post


Link to post
Share on other sites

hi neighbours,

anyone know any contractor that do cement screeding?

currently renting unit and contract ending december 2007, cannot

renew cause must sign 6 month contract... :yamseng: owner increase rent price some more from 1.3k to 2k :)

need to move in 26B by then, else no place to put stuff.

thanks all !

 

Share this post


Link to post
Share on other sites
Hi all,

We collected our keys last sat, went in and check, there is like no defects with the exceptions of the electrical sockets, nearly all of them are faulty..

Can I also ask will HDB replace the windows if they are rusty?? I have one handle which is rusty liao..

binzz, maybe you can ask them to help u relocate the new sockets @ yr desired places even... no need to pay yr ID to relocate the points for you :yamseng:

rusty handle better get replaced or else broken liao, dunno how u gonna close the window

 

Share this post


Link to post
Share on other sites
hi neighbours,

anyone know any contractor that do cement screeding?

currently renting unit and contract ending december 2007, cannot

renew cause must sign 6 month contract... :) owner increase rent price some more from 1.3k to 2k :curse:

need to move in 26B by then, else no place to put stuff.

thanks all !

Hi Owens..

Welcome.. to the forum

You can request HDB to do cement screeding for you - FOC :yamseng:. :curse:

Mind me kaypo a bit? Btw, where are you renting the unit now?, and how big is the flat?.

Thanks...

Edited by gadgetgal
 

Share this post


Link to post
Share on other sites
binzz, maybe you can ask them to help u relocate the new sockets @ yr desired places even... no need to pay yr ID to relocate the points for you :yamseng:

rusty handle better get replaced or else broken liao, dunno how u gonna close the window

Hehe, good idea leh.. We haven't submit the defect list yet, still wanna go through and check for the hollow tiles.. Brought a chair there on sunday when i brought my parents to see.. Will check on deepavali.. hehe..

 

Share this post


Link to post
Share on other sites

renting in yishun, it's 3+1 rooms, :) rental increase these days really off the scale.

thanks for the info, but i can't wait for hdb screeding, it will take at least 3 weeks.

based past release schedule, 26B earliest release will probably be dec 1st week.

need enough time to do very basic renovation.

Hi Owens..

Welcome.. to the forum

You can request HDB to do cement screeding for you - FOC :yamseng:. :curse:

Mind me kaypo a bit? Btw, where are you renting the unit now?, and how big is the flat?.

Thanks...

 

Share this post


Link to post
Share on other sites
think mine will finish in early dec. i'm really taking my own sweet time. reno works will stop for this week coz my dad went hong kong for a tour. hahah :yamseng: living room tiles should complete next week. Kitchen cabinet/wardrobe probably end of nov.

btw, i'm not from sers. i got the flat from balloting... :)

Ooopss....sorry sorry.. i tot u from SERS. Hee

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×