I wanted vinyl flooring for my kitchen, living hall and bedrooms. My cement screed was done at a lower height, shortage abt 7mm - 10mm from my kitchen existing tiles. I was unable to have my vinyl levelled between kitchen and living hall. They have to put on an pvc cap between kitchen and living hall. Is there anyway to fix this? I was expecting the whole flooring to be of the same level. 

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Normally kitchen will be at a lower level than living room since it is a wet area so as to prevent water from flowing to living room in case of washing the floor. Only way to fix is to add more screed to same level as living room

 

Share this post


Link to post
Share on other sites

both. too thin will not provide enough strength to the screed. too thick may also crack due to the uneven drying of the screed.

you can search online for data sheets from screed manufacturers and they normally recommend thickness of 10mm to 40/50mm. if need more then usual case is pour concrete to top up then apply screed.

of cos if you insist on doing it and am willing to bear any consequences of it and indemnify your contractor I don't think he will not do it if he is paid. it's just that if anything happens, he may tell you, "I told you so" 

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×