hello wyx03_2002 ! im from Costa Ris too !

but still waiting for keys... :(

look forward to seeing more pictures ! :D

Edited by beehoon
 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Hi abbytan,

I used Oops. Overall, quite satisfied with the service, especially they deliver to your door step. Unlike Daigou65, we will need to collect the goods at one of their pickup location chosen by you.

You can manage everything online, and they are quite responsive in email. They also have a local mobile number for enquiries, but not as responsive though.

Planning to go for 2nd round of purchase...got addicted after my 1st round of purchase with all goods delivered in good condition :good:

 

Share this post


Link to post
Share on other sites

Very sharp eagle eye .....We are on the highest 13th floor, but the ceiling height is only different by ~10cm. I think the highest floor of the older flats were ~20cm taller.

We decided to take the highest floor so we won't see the drainage/water pipes running down from the flat unit above. But we are taking the risk of lower water pressure as many have feedback in the forums.

 

Share this post


Link to post
Share on other sites

Some of the defects that we reported to BSC on 15/9. All have been rectified as we inspected yesterday except the uneven mosaic tiles in both bathrooms. Talked to the BSC officer and inspected the uneven mosaic tiles together with their technician. Was assured that it will be done by Sat. So, going to make another inspection on Sun to make sure things are really done and no more delay.

To those who are planning for their reno and move in date, you may want factor in ~3 weeks for defects rectification by HDB. We wasted 2 weeks for them to rectify the defects at their slow pace with the reasons of tight schedule and always "in progress" status. Don't be surprise if you are asked to wait for another 2 weeks for them to screed the flooring

gallery_62932_509_75652.jpg

30/12/2014: Edited to consolidate all photos due to limitation in gallery, and updated with post-reno photos. Feel free to pm me if you need photos at certain places in the house.

Edited by wyx03_2002
 

Share this post


Link to post
Share on other sites

30/12/2014: All photos in this page have been consolidated in post #21

Edited by wyx03_2002
 

Share this post


Link to post
Share on other sites

Inspected this evening after the HDB sub-contractor touch-up on the uneven mosaic tiles. The uneven tiles in the MBR bathroom look acceptable, but the uneven tiles in the common bathroom just moved from one area to another area :curse:Decided to KIV this defect for now and push for floor screeding and reno to start early next week.

Was told by the HDB officer that this is one of the most common problem in the new flats in Costa Ris....

 

Share this post


Link to post
Share on other sites

2nd version of the 3D photos from my ID. Will make some changes in the color but probably no more 3D as it takes too long to get updated.....

gallery_62932_509_52353.jpg

gallery_62932_509_200167.jpg

30/12/2014: Edited to consolidate all photos due to limitation in gallery, and updated with post-reno photos. Also commented in the photos with all the loose promises and mismanagement of some reno items

Edited by wyx03_2002
 

Share this post


Link to post
Share on other sites

30/12/2014: All photos in this page have been consolidated in post #24

Edited by wyx03_2002
 
  • Like 1

Share this post


Link to post
Share on other sites

Started floor screeding on 30/9 and 3rd round of common bathroom's uneven mosaic tiles rectification. But no luck....

HDB sub-contractor seemed to start late and got the MBR flooring done. No progress on the other 2 bedrooms. They also left the MBR windows wide open. Wonder if that was on purpose to let the cement dry or forgotten to close :dunno:

Gave up to let HDB sub-contractor to keep rectifying the uneven mosaic tiles while delaying all other reno works. Informed BSC to hold on the 4th round of rectification in order for us to start the floor screeding and reno works. Put this under KIV :bangwall:

Hopefully the electrical works on this coming Fri and Sat can progress smoothly..... :bow:

 

Share this post


Link to post
Share on other sites

Didn't have much time to upload photos since I am here in Taiwan for oversea work assignment for a week. Leave the reno to ID and wife while getting updates from them through skype and emails. Ran into quite a lot of trouble mainly caused by the building structure where the kitchen flooring is higher than the living/bedrooms floor level. As per ID, the kitchen flooring will be higher than the living room flooring once overlaying the kitchen tiles. So, we have to raise the living room floor level slightly while not obstructing the bomb shelter's door. But will have to trim the main entrance door.....seems like the HDB construction quality really needs a 3rd party to watch over them :(

MBR aircon trunking box up....wonder if there will be any problem next time when servicing the aircon fan unit with such a limited space.

gallery_62932_509_299354.jpg

30/12/2014: Edited to consolidate all photos due to limitation in gallery, and updated with post-reno photos.

Edited by wyx03_2002
 

Share this post


Link to post
Share on other sites

Aircon trunkings in MBR. Not a perfect routing but thoughtful and practical enough. Will discuss with ID to reroute the small drainage PVC.

gallery_62932_509_19102.jpg

BTW, an advice to home owners who will install their aircon in early reno phase. Make sure your aircon fan units are properly wrapped up during the reno works. Otherwise you will need to spend extra time to vacuum the dust out from the up-facing suction holes before you can use them.....a hard lesson learned :(

Edited by wyx03_2002
 

Share this post


Link to post
Share on other sites

Woah! Yr kitchen looks like a runway! I love the lightings under the cabinets!

(Somehow ID drawings can be misleading. But that's their rice bowl)

ya...but that 'runway' costs a lot because we will need to pay for approx 57ft of top+bottom cabinets and quartz table top. Our ID brought us to visit his on-going project with the kitchen cabinets' downlight, and we really like it despite having to give up quite significant amount of storage space. But we eventually have to pass this design idea because we have cement base for our kitchen sink and stove, which have to be sit on the floor. Instead of 50%-50% different design of bottom cabinets, we go for the normal but more practical design :bleah:

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×