Songz

3 Room Resale

Recommended Posts

Not much update this week as not much work was done in the early week

Platform for Carpentry, Fridge, Washing Machine + Kitchen Floor Tiling Done

14253156572_4454445698_m_d.jpg14232184746_69cc4ea3ac_m_d.jpg14232184526_eb25e73bdd_m_d.jpg

Tiles for both MBR & Common Bathroom Done

14142449376_108e12d966_m_d.jpg

Aircon Piping (Done by Tim from this Forum) will be laid and will be completed by this weekend.

14068753937_18307f3285_m_d.jpg14068753957_59305f822e_m_d.jpg

**Next week Water & Gas pipe will be laid follow by the start of False Ceiling & some Box-Up.

 
  • Like 1

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

This is the part 1 of warzone... Part 2 is the moving of many many stuffs and unpacking. ;)

Hahaha ~

Totally agree on it but let me finish this phase of the warzone first ~ :lol::D

 

Share this post


Link to post
Share on other sites

New gas pipe have been laid.

14299474303_77cbd54161_m_d.jpg

Aircon piping have also been done

14256172796_0b56d76710_m_d.jpg14275953811_82241f2348_m_d.jpg14092729007_2b2474f8ce_m_d.jpg

In order to hide most of the aircon trunking & aesthetic purpose, the ID & Aircon installation guy manage to persuade me to fix the aircon for the living room to be just above the storeroom door. (Picture as per below - Beside the piping that stick out))

The installation guy claimed that 18K BTU will be able to cool the living room easily by adjusting the wind to blow below the beam in front and into the living room.

(*Hope they are right on this)

14092631519_32b7896ffe_m_d.jpg

 

Share this post


Link to post
Share on other sites

I have Dunlopillo vouchers as per below.

The expiry date for purchase is 30th June.

If anyone is interested, you can collect it from me.

14139708548_8ff0147863_z_d.jpg

 
  • Like 1

Share this post


Link to post
Share on other sites

Not much work has been done except for the Box-Up and false ceiling.

Living room Box-Up (Need to wait for Fiber to be installed to continue to Box-Up) & False Ceiling

14330429691_61703db882_m_d.jpg14333031574_183958c850_m_d.jpg

Kitchen Box-Up

14333766965_b355707901_m_d.jpg

MBR Box-Up

14333031474_26d2442ba0_m_d.jpg14147264857_a3f0640c97_m_d.jpg

For the piping above the door, it will not be able to box-up as its too near to door :( .

Hope it will not be obvious after painting works is done.

Edited by Songz
 

Share this post


Link to post
Share on other sites

Sorry but I have been busy with work + just went to oversea for work (The network there is so bad that I don even bother to on my cpu)

Below are the updates so far :

14484353271_5af0a3e0fd_m.jpg14484355051_6d5337274c_m.jpg

First coat of painting have been done.

OpenNet have also finally come and install the point (Delay my BoxUp by the window - Not shown here)

14301148848_801ec8c41d_m.jpg

First coat painting for room is done and door for bathroom is installed

14301091260_3425ff7d4e_m.jpg

Tiling for Kitchen is done + Rubbish chute installed (Below does not have tiles as there will be carpentry works to cover it)

The top piping part will be BoxUp.

 

Share this post


Link to post
Share on other sites

Due to restriction on number of photos per post thus the 2nd post.

14301091590_d108d59787_m.jpg

Ledge is completed (This is for me to put my leg up after bath to dry with towel) in MBR

14486489562_ce96405a17_m.jpg

Sanitary (Toilet Bowl & Basin+tap is installed)

Due to the small size of the MBR, I have decided to use a corner basin to save space)

14301109799_20c56ff21c_m.jpg

Sanitary (Toilet Bowl & Basin+tap is installed)

Space constraint again but at least its bigger than MBR bathroom thus able to place the basin in front of the toilet bowl.

*For the rack, water heater and etc, it will be installed at a later date

 

Share this post


Link to post
Share on other sites

Most of the lights & switches are installed (Some can only be installed after carpentry) + Fan

One of the switch have defect and will inform ID about it today when meet him tonight.

14613487321_8e67af9c4b_n.jpg

 

Share this post


Link to post
Share on other sites

Most of the lights & switches are installed (Some can only be installed after carpentry) + Fan

One of the switch have defect and will inform ID about it today when meet him tonight.

14613487321_8e67af9c4b_n.jpg

Nice ...... bro, no cove lighting in the false ceiling??

 

Share this post


Link to post
Share on other sites

Nice ...... bro, no cove lighting in the false ceiling??

The only cove light (If it counts) is the straight ledge you see in the picture.

Not really a fan of cove light and the main purpose of it in the picture is to cover the beam

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×