Pokz1981

Reno @ Kovan Maisonette

Recommended Posts

Nice furniture pieces.

It was a great challenge for my husband & myself to search for furniture with 3 monsters along, haha.

Oic... Thanks for your reply! Btw, really nice furniture! Am loving all the wood grains!

Thx alot, i took the advice from renotalk postings and went around searching rather than doing buit-in

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

hee i was about to ask the same thing

the burger bedframe is def from ethnicraft

can't wait for mine to arrive

great choice on your furniture! are they from ethnicraft?

 

Share this post


Link to post
Share on other sites

hee i was about to ask the same thing

the burger bedframe is def from ethnicraft

can't wait for mine to arrive

Yes, they are. The first few were from "The originals" but later did i realised that Ethnicrafts were the suppliers.

 

Share this post


Link to post
Share on other sites

Its getting exciting to see progress daily. With all tiles and walls being hacked. Restoration for new walls have begun. Almost all new windows are up except the balcony area. Hoping to see my tiles delivered soon for tiling works to start :notti:

Kitchen wall tiling, the little entrance to the back in the centre is to the storeroom. While the yet to be tiled up part would be the smaller size study room with the entrance marked with no brick walls in between

gallery_54308_84_105312.jpg

slightly better view here for the entrance to the store

gallery_54308_84_47139.jpg

The storeroom. Not really very big but at least better than none to put all the junks here away from view.

gallery_54308_84_68928.jpg

Masterbedroom toilet extended over to the common bathroom

gallery_54308_84_103911.jpg

To the left of the master toilet, cement filled after all the hacking

gallery_54308_84_5836.jpg

 

Share this post


Link to post
Share on other sites

Yes, they are. The first few were from "The originals" but later did i realised that Ethnicrafts were the suppliers.

Good to know! The similarity never registered in my mind.

 

Share this post


Link to post
Share on other sites

Floor tiles are delivered but works are still in progress after the hollow walls are up. Cement screed on those walls and also flooring for bedroom 2 are done.

4k8j.jpg

pd3o.jpg

bmvg.jpg

 

Share this post


Link to post
Share on other sites

Hi, we are planning to use roller shutters too. May I know which company you engaged for them? And how much you paid for it? :)

Hi Ferddy03,

Initially i wanted to use Paul Aluminium as this is the only one i can google and find. But seems like my contractor can get someone to come down and do a measurement and quote. So maybe i will let you know thereafter.

 

Share this post


Link to post
Share on other sites

Progress has been slow but since most of the toilets are tiled up. tiling for living have started. Tiling for all areas in 2nd floor have not started and i have no idea when it would be. Tiling for lower floor should all be done up by this week.

c0ct.jpg

tiling for common bath

qwqv.jpg

Tiling for master bath

jj18.jpg

 

Share this post


Link to post
Share on other sites

Tiling is going fast ever since toilets are done. electric wiring has also started. Heard from ID that measurement of glassworks was also done today. however, still no news of parquet laying for upper floor yet. All tiles have been finalised including the mosaic tiles for the backsplash. Selected 3 different colours to do mixing and matching on tuesday, keeping fingers crossed that end result will look good.

Mosaic tiles selected

cuey.jpg

Tiling for kitchen area

289h.jpg

ete9.jpg

 

Share this post


Link to post
Share on other sites

Tiling is going fast ever since toilets are done. electric wiring has also started. Heard from ID that measurement of glassworks was also done today. however, still no news of parquet laying for upper floor yet. All tiles have been finalised including the mosaic tiles for the backsplash. Selected 3 different colours to do mixing and matching on tuesday, keeping fingers crossed that end result will look good.

Mosaic tiles selected

cuey.jpg

Tiling for kitchen area

289h.jpg

ete9.jpg

Our wood tiles look really similar

 

Share this post


Link to post
Share on other sites

Ok, its been awhile since I last posted. Alot have been done throughout but progress is not that fast anyway.

- Conduit was laid underneath the floor tiles for the opennet cable to go straight through to the TV area.

- Floor tiles are all done including skirting (very good job actually)

- Windows are installed except lower kitchen toilet as I need to box up some water piping before the measurement can be taken

- Water storage heaters are installed. Rheem brand was used (not really sure its reliability as I was not consulted prior to installation. Quite pissed on this actually :curse: but I just bear with it. Initially, they tried ot install 10gallons (38litre) for both upper and lower floor. However, after going back to complain that i do not need such huge amount for downstairs, it was changed. The placing of the heater was also redone as they initially installed above my upper floor common bath which makes the whole space looks quite low and ugly. Thereafter, it was taken down and shift out to the bathroom entrance area

5d9.JPG

- Electrical wirings are all done except some minor changes with the switches model selected.

- Aircon piping were run and installed too. Waiting for final installation. This is one of the huge headache of running the pipings. Good thing is false ceiling will be use to conceal them.

- Rain shutter was installed yesterday. Still ok, though i have not tested it myself

- Last but not least, they are currently doing the parquet floorings for the upper floors and staircase. Once all done and varnished (3 days cannot work for the upper level)

Pictures time.

Living room facing kitchen

ebi9.jpg

Study room

jhec.jpg

Study room tiles, same as kitchen

6mbb.jpg

Kitchen view overlooking balcony

qze2.jpg

Common bath shower area on the left and Master bath on the right

97vo.jpg

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×