ABT 0 Report post Posted December 8, 2012 I have engage Sleek Interior Pte Ltd from Roxy Square(#02-38) at East Coast Road for some renovation works. It's been a 'nightmare' working with them the last 3 weeks. Works are hardly progressing everyday and they (Francis/Ken) are not picking up my calls except lots of SMS after long periods without resolving anything. They are avoiding my calls. They keep putting me as a monkey to be tossed around between them for clarification, ...,etc. They keep asking for additional charge and now says they need another 3 weeks. The original schedule is supposed to be a 1 week completion and 1 week touch up work. Pitifully, I made a bad decision to pay them 85% when they start work. Does anyone knows how and who I should escalate this OR how I can get back my money for all other works that they have not done ? Share this post Link to post Share on other sites
RemyLebeau 0 Report post Posted December 9, 2012 I have engage Sleek Interior Pte Ltd from Roxy Square(#02-38) at East Coast Road for some renovation works. It's been a 'nightmare' working with them the last 3 weeks. Works are hardly progressing everyday and they (Francis/Ken) are not picking up my calls except lots of SMS after long periods without resolving anything. They are avoiding my calls. They keep putting me as a monkey to be tossed around between them for clarification, ...,etc. They keep asking for additional charge and now says they need another 3 weeks. The original schedule is supposed to be a 1 week completion and 1 week touch up work. Pitifully, I made a bad decision to pay them 85% when they start work. Does anyone knows how and who I should escalate this OR how I can get back my money for all other works that they have not done ?Isn't the payment supposed to be progressive payment? Try going CASE seek assistance. Share this post Link to post Share on other sites
Dorawang 0 Report post Posted December 9, 2012 If all else doesn't work, try small claim tribunal. Share this post Link to post Share on other sites
Sygnur 0 Report post Posted December 9, 2012 I think that the progressive payment... 10% upon confirmation( sign up with the company),40% when work starts( id/contractor come take measurement, do markings, painting, tiling work is being carried on, etc) 40% before carpentry goes into fabrication( design finalised, etc), 10% upon completion.For the 1st 3 stages already 90% being paid. So 85% might be for the first 3 stages.ABT, i hope u have everything in black and white. But, even going to case/sct wont help much. The loopholes exist such that scruplous id/contractor can really escape. Even reporting to police will be treated as civil case n nothing much can be done. I know this is disheartening, but consumers law here is really weak.( based on what my neighbour who had been conned ). Share this post Link to post Share on other sites