Wolfgang11sg 0 Report post Posted June 7, 2012 Dear all,We are thinking of hacking the floor and wall tiles of our common toilet., just wonder how long does it take to do a toilet. My contractor has 9 working days to do so but he kept saying it's not possible to complete. Am so wonder why it takes more than two weeks to complete a toilet? No fancy toilet design, just simple standard of hacking and relay tiles only.Thank you Share this post Link to post Share on other sites
taichipanda 3 Report post Posted June 7, 2012 (edited) Dear all,We are thinking of hacking the floor and wall tiles of our common toilet., just wonder how long does it take to do a toilet. My contractor has 9 working days to do so but he kept saying it's not possible to complete. Am so wonder why it takes more than two weeks to complete a toilet? No fancy toilet design, just simple standard of hacking and relay tiles only.Thank youhacking - 3 dayscement & plastering - 2 dayswaterproofing - 2 dayslaying of floor and wall tiles - 3 daysfitting & fixtures - 2 days3+2+2+3+2 = 12 days = 6 days per week = 2 weeks. Edited June 7, 2012 by taichipanda Share this post Link to post Share on other sites
Wolfgang11sg 0 Report post Posted June 7, 2012 hacking - 3 dayscement & plastering - 2 dayswaterproofing - 2 dayslaying of floor and wall tiles - 3 daysfitting & fixtures - 2 days3+2+2+3+2 = 12 days = 6 days per week = 2 weeks.I see, thank you for the information. Maybe I should consider overlay instead. Share this post Link to post Share on other sites
Tiler Seng 57 Report post Posted June 7, 2012 I see, thank you for the information. Maybe I should consider overlay instead.i am renovating a toilet for 3 weeks, another toilet started work yesterday, it's going to be another nightmare for this old-time client don't have to feel suprise, we are trying to make something different from others.Photos...? later after full completion lah Share this post Link to post Share on other sites
Wolfgang11sg 0 Report post Posted June 7, 2012 Still thinking, sinercely might just overlay... No place to stay for three weeks.Will load photo after completion Thanks bros Share this post Link to post Share on other sites
Lin 0 Report post Posted June 11, 2012 Hi!Can share how much is the normal rate for overlay floor + wall tiles?Can also share your contractor contact?Tks! Share this post Link to post Share on other sites