herbalteh 0 Report post Posted March 20, 2012 (edited) Hello all,Finally got my keys in Mid Nov 2011. Rushed happily to HDB to get my keys.here is my floor planHere are our lst visit to the houseLiving roomCorridor to all rooms Edited March 21, 2012 by herbalteh Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 20, 2012 (edited) Master roomRoom 1Room 2 Edited March 21, 2012 by herbalteh Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 20, 2012 (edited) MBR Toilet Edited March 21, 2012 by herbalteh Share this post Link to post Share on other sites
yapht 0 Report post Posted March 21, 2012 congrats on getting your keys! Share this post Link to post Share on other sites
ayazumi 0 Report post Posted March 21, 2012 (edited) Your 拜拜 ceremony is similar to mine. Huat kueh, pineapple, orange, joss sticks, candles, joss papers.Congrats for getting your own home Edited March 21, 2012 by ayazumi Share this post Link to post Share on other sites
Takeyu 0 Report post Posted March 21, 2012 congrats on getting your keys!! =) Share this post Link to post Share on other sites
beluga 1 Report post Posted March 21, 2012 Is this the unit near to Polyclinic? Anyway, congrats to your new unit! Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 Is this the unit near to Polyclinic? Anyway, congrats to your new unit!Thanks to all.Nope...this one, is at sunshine court... Will post more tonite. Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 Main ToiletKitchenService Yard Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 (edited) Spent the months of Nov 2011 to Feb 2012 looking for IDs / Contractors. That took up alot of our time....On the positive side, we did learn quite a fair bit of stuffs, the needs and wants, the good and bad....Below are a list of IDs that we went to...Sum Hup (located near North Link Building) - This is a company with very good workmanship...Great carpentry...Comfort level is ok as this is the lst company we visitedOutlook Exterior (or Interior) - Recommended by my ex colleague (3rd company we visited, comfort level is good, 7/10)Home Success - Managed to know them while going to Expo Exhibition (2nd company we visited, comfort level 1/10), this is a very long story on what happened, dont wish to bring it up again...MOD - Recommended by my gf's fren (6th company we met - Great innovation ideas, but exceed our budget, comfort level 7/10)North West Interior - Recommended by my gf's colleagues (4th company we met 7/10)BLue and Blve - recommended by my customer (5th company we met 6/10)After so many months of negotiation, exhaustion and frustrations sets in. We are quite tired and felt quite ''sian'' by the delay to start work. This is further hampered by the fact that CNY is approaching and every ID / contractor is rushing to complete on schedule. Hence, we decided to start only after CNY....1.5 weeks after CNY, we finally settled for a guy named, SOH. Edited March 21, 2012 by herbalteh Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 1st week of March, RENOVATION STARTS!!Here are some updated pictures!Living RoomMBR Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 ROOM 1ROOM 2KitchenService Yard Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 One day later.....More pictures!MBRLiving Room - Forget to take pictures....Room 1Room 2Kitchen Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 Time to install Air Con!Route from Air con ledge all the way to room 2AC ledge into MBR toiletUnit planted in MBR(fixture in MBR) Share this post Link to post Share on other sites
herbalteh 0 Report post Posted March 21, 2012 Into the main toiletInto room 1 Share this post Link to post Share on other sites