turtledriver 0 Report post Posted February 10, 2012 Hi everyone,Would like to get some of your kind advise.If I would like to do my own project management for my entire renovation, what should be the proper sequence of events like? Is it like the following:a) Install airconb) Run electrical wiringc) Paintingd) CarpentryHope to get you kind advise soon on this. Thank you. Share this post Link to post Share on other sites
Tiler Seng 57 Report post Posted February 10, 2012 Hi everyone,Would like to get some of your kind advise.If I would like to do my own project management for my entire renovation, what should be the proper sequence of events like? Is it like the following:a) Install airconb) Run electrical wiringc) Paintingd) CarpentryHope to get you kind advise soon on this. Thank you.Hi Turtle,1. electrical2. AC3. Painting4. carpentry Share this post Link to post Share on other sites
turtledriver 0 Report post Posted February 10, 2012 Hi Turtle,1. electrical2. AC3. Painting4. carpentryThanks for the helpful response as usual Tiler Seng Share this post Link to post Share on other sites
tedlim 0 Report post Posted February 27, 2012 When should floor works(wet/dry) be done in this sequence? Share this post Link to post Share on other sites
Tiler Seng 57 Report post Posted March 1, 2012 When should floor works(wet/dry) be done in this sequence?depending on site situation, 0.5 or 2.5 Share this post Link to post Share on other sites
padlee 0 Report post Posted March 2, 2012 hi may i know when should ceiling works be done? before or after electrical? Share this post Link to post Share on other sites
polarlim 0 Report post Posted March 2, 2012 My guess would be electical first as the ceiling need to cover the cable. Just my guess Share this post Link to post Share on other sites