Takeyu 0 Report post Posted December 19, 2011 Continuation of the 3D drawings,As mentioned previously, we adopt our ID idea of the MBR which we absolutely like though it could look a bit cramped for us due to the small room. but heck it, let just do it!Entry to the MBRthe black color would be changed to purple color as shown in the next picture.MBRTV console and design to go with the living room design hahaMBR ToiletOverlaying the wall tiles as the current tiles really look ugly in our opinion. The side boxes wun be so spacious in real life though. hahah Share this post Link to post Share on other sites
piknik 1 Report post Posted December 20, 2011 (edited) So roughly all these will cost you $25-30k? I like the hot-pink shoe cabinet . Is it with polka dot pattern? You will really change the toilet sink? I want to as well, just dread the process of buying/choosing a sink... Haiz....Since u have platform for ur bedroom, do u make it a storage solution as well? It would be handy if u have/will have children. Edited December 20, 2011 by piknik Share this post Link to post Share on other sites
Takeyu 0 Report post Posted December 20, 2011 (edited) So roughly all these will cost you $25-30k? I like the hot-pink shoe cabinet . Is it with polka dot pattern? You will really change the toilet sink? I want to as well, just dread the process of buying/choosing a sink... Haiz....Since u have platform for ur bedroom, do u make it a storage solution as well? It would be handy if u have/will have children.yup ard 30k... haven't add the electrical all tat =\yeah its abit 3D for the shoe cabinet ba not exactly polka dots...Definitely lor, we been scouting for a sink and toilet bowl that it's a **** tedious process coz got certain dimensions to align to. hahahaNope, we din make it a storage solution my fiancee dun really fancy the idea of it and budget wise , it will be abit siong on us... Edited December 20, 2011 by Takeyu Share this post Link to post Share on other sites
Takeyu 0 Report post Posted December 20, 2011 We arrange with the ID to start our reno in late Nov / early Dec. But b4 that, he dropped a bomb on us by saying that he has quit the ID firm and be starting up his own firm. Luckily he was responsible enuff to says that he will still be the one to manage this project till the end, if not, my fiancee will go crazy sia! hahahaAnyway he gave us a schedule on what will be done each day... and it was seriously fast and furious for us as we haven't get our electrical appliances, hob all tat... hahahere are some reno in progress picsKitchen baseWasher baseMBR Toilet Overlaid TilesLiving False Ceiling Electrical Points Share this post Link to post Share on other sites
piknik 1 Report post Posted December 20, 2011 AhW fast n furious. I didn't like the storage idea at first. But observing families with kids, I have to say, platform with storage will save us later on. Less space clutter, less furniture, .But I like systemind platform only. Hahaha..... Share this post Link to post Share on other sites
Takeyu 0 Report post Posted December 21, 2011 AhW fast n furious. I didn't like the storage idea at first. But observing families with kids, I have to say, platform with storage will save us later on. Less space clutter, less furniture, .But I like systemind platform only. Hahaha..... yeah definitely ba, with storage platform should have more space to store all the barung barung. haha Share this post Link to post Share on other sites
Takeyu 0 Report post Posted December 21, 2011 After the overlaying of toilet tiles and constructing the bases, next up would be the construction of hte false ceiling. was there on the day when ID was giving instructions to the workers on how to do it as the shape was diff frm what they usually do. here are some picsLiving Room False Ceiling MBR False CeilingLiving Room False Ceiling up!MBR False Ceiling up!MBR Toilet Door Changed. Share this post Link to post Share on other sites
Takeyu 0 Report post Posted December 22, 2011 Most lights have been delivered except for the hanging crystal lights which be delivered at a later stage. Installation of the downlights and cove lights are completed. Here are some pics of the lights.Coming from the entranceFoyerLiving Room [From Foyer View]Living Room [Another Angle]Common Toilet Share this post Link to post Share on other sites
Takeyu 0 Report post Posted January 5, 2012 Here are some more pics of the lightnings around the house.Passage Way LightsMBR LightsBR2 LightsGot 3 Mode to choose from. Warm Light [LED], White Light then White plus Warm.BR3 LightDesign-wise, same as BR2 but this one will come without the LED lights.Service YardMy partner chose this coz she think its cute due to the resemblance to dog dish. hahaha Share this post Link to post Share on other sites
Takeyu 0 Report post Posted January 5, 2012 As it was near the year end, not much work was being done for this period of time but they did a 1st round of washing though. My ID also inform us that they be doing up the laminated platform on 4th Jan.Therefore we decided to go take a look that day to see the finished product and we were pleased with it. Here are some pics of it.MBR PlatformMBR Platform with Lightnings onAfter all this, we be left with mostly carpentry and other misc stuffs. All this would continue after CNY which would buy us some time as we have yet gotten the toilet accessories all that....Doing reno and planning for a wedding both at the same time is so mentally draining! but hope everything turns out fine for us! Share this post Link to post Share on other sites
Terencetcw 0 Report post Posted January 5, 2012 wowo great progress~ Can i know what is the reno schedule like?1) Demolishing2) Hacking3) Piping4) Wiring.. Share this post Link to post Share on other sites
potatoes 0 Report post Posted January 6, 2012 HI Takeyu, how is your reno going? I happen to see your 3D design .... looks really lovely and great colour combinaion. Are you getting what you see in your 3D drawing.It will be exciting to see your final product. Share this post Link to post Share on other sites
NeoBY 1 Report post Posted January 6, 2012 Hey!! Mine is at Rivervale Drive. I probably start renovation after CNY. Share this post Link to post Share on other sites
Takeyu 0 Report post Posted January 6, 2012 wowo great progress~ Can i know what is the reno schedule like?1) Demolishing2) Hacking3) Piping4) Wiring..Hmmm the schedule ish not with me now... but for mine, there's not much demolishing as its a new flat... If i'm not wrong, here's a draft schedule of how it proceeds:Removal of MBR toilet and sink for overlaying of wall tilesTiling starts, Fridge, kitchen and washer base includedWiring 1stPiping then.Air-con trunking 1st trip Setup of false ceilingInstallation of down and cove lights. (Hanging lights later stage)1st coat of paint1st round of washingMBR Laminated platformWould meetup with ID soon for the schedule after CNY... so far everything is up to date and looking gd.We still need to get the various toilet accessories and stuff 1st though. hahaha Share this post Link to post Share on other sites
Takeyu 0 Report post Posted January 6, 2012 HI Takeyu, how is your reno going? I happen to see your 3D design .... looks really lovely and great colour combinaion. Are you getting what you see in your 3D drawing.It will be exciting to see your final product.hey potatoes, everything going well so far. not much hiccups yet, but cross fingers 1st! ahahaso far, it has been close to the 3d drawings. For the colors, we will see more of it when the carpentry starts. Yeah me and my wife are looking fwd to the final product too! Will definitely post more pics when carpentry starts :0 Share this post Link to post Share on other sites