Living & Main Entrance Amount

custom made 4ft full height shoe cabinet in laminate finish c/w casement & ABS triming $960

custom made 2ft settee c/w PVC cushion in laminate finish c/w cabinet & ABS Triming $460

custom made 6ft full height feature wall in laminate finish (designer piece) $1080

custom made 6ft TV console in laminate finish c/w drawer $720

custom made 10ft L -Shape Bar top in laminate finish $1600

custom made 7.5ft display cabinet in laminate finish with open shelves $1875

Master Room

custom made 6ft full height wardrobe in laminate finish c/w casement & ABS triming $1260

Supply labour and material to install TV Console? TBC

Supply Labour and material to install vender door c/w stopper, handles and lock $320

Bedroom 2

Supply Labour and material to install vender door c/w stopper, handles and lock $320

bedroom 3

Supply Labour and material to install vender door c/w stopper, handles and lock $320

Kitchen

custom made 16ft suspended bottom kitchen cabinet in laminate finish $1920

c/w casement door & ABS triming without Solid Surface

custom made 10ft top hang kitchen cabinet in laminate finish $1200

c/w casement door & ABS triming without Solid Surface

supply labour and material to create 1m x 0.55m wall support at kitchen door top $150

supply labour and material to install 10mm clear tempered sliding glass door $750

Master Toilet

custom made 6ft suspended vanity cabinet in laminate finish $720

c/w casement door & ABS triming without Solid Surface

Common Toilet

custom made 3ft suspended vanity cabinet in laminate finish $360

c/w casement door & ABS triming without Solid Surface

Miscellaneous

All carpentry with casement door c/w FOC Blum soft closing hinges FOC

kitchen cabinet will c/w 1 no. dish rack and cutlery tray FOC

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

hi thanks for the advise, just asking what you mean is it everything? then the market rate is around how much per feet?

hi...care to share who is yr ID? my kitchen is 10 bucks more than yrs per foot run.

 

Share this post


Link to post
Share on other sites

Hi all

I need your advice on the quotation given to me below. Thanks!

A Design Services

1 Interior Design and Space Planning.

2 Furniture layout plan.

3 Perspective carpentry drawing.

4 Selection of color, material and accessories.

5 Consultation and project management.

6 Site co-ordination and supervision.

7 Decoration advice.

B Hacking Works

1 To hack off existing kitchen & 2 bathrooms flooring.

2 To hack off existing kitchen & 2 bathrooms wall tiles.

3 To hack off existing 50mm kitchen, fridge & washing machine base

4 To dismantle existing kitchen cabinets.

C Masonry Works

1 Supply labour & material to lay 300mm x 300mm heavy duty non-slip homogenous floor tiles for kitchen.

2 Supply labour & material to lay 600mm x 300mm homogenous wall tiles at kitchen area.

3 Supply labour & material to lay 300mm x 300mm heavy duty non-slip homogenous floor tiles for 2 bathrooms.

4 Supply labour & material to lay 600mm x 300mm homogenous wall tiles at 2 bathrooms.

5 Supply labour & material to lay waterproofing membrance for kitchen floor.

6 Supply labour & material to lay waterproofing membrance for 2 bathrooms floor.

7 Supply labour & material to construct 50mm kitchen cabinet base with side tiling.

8 Supply labour & material to construct 50mm washing machine base with side tiling.

9 Supply labour & material to construct 50mm fridge base with side tiling.

D Carpentry Works

1

Supply labour & material to fabricate 20ft designer's kitchen cabinet in laminate finish c/w ABS trimming casement door, 1 set of 2 tier stainless steel dish rack and cutlery tray.

2 Custom made 10ft(L) solid surface worktop c/w backsplash, sidesplash & front profile.

3 Supply labour to install cooker hood & hob.

E Doors/Gate Works

1 Supply labour & material to install acrylic bi-fold door at 2 bathrooms.

F Plumbing Works

1 Supply labour & material to run whole unit wiith stainless steel piping (cold water points only)

2 Supply labour & material to install concealed drainage pipe for kitchen sink.

3 Supply labour & material to install concealed drainage pipe for washine machine.

4 Supply labour & install kitchen sink & tap.

5 Supply labour to install 2 nos. wash basin & tap for 2 bathrooms.

6 Supply labour to install 2 nos. toilet sitting bowl for 2 bathrooms.

7 Supply labour to install 2 nos. toilet shower mixer for 2 bathrooms.

8 Supply labour to install 2 sets of instant heater or 1 set of storage heater.

9 Supply labour to install 2 sets of bethroom accessories.

G Painting Works

1 Supply labour & material to paint whole house interior & ceiling with Nippon Vinilex 5000.

2 Supply labour & material to paint door frames & pipes with Nippon Gloss paint.

H Miscellaneous Works

1 Supply labour & material to do chemical cleaning to whole house upon completion of works.

2 Supply labour & material to lay corrugated paper for protection upon completion of tiling works

Cost = $15888

Others

1 Supply labour & material to install propose false ceiling **** area. $1850

2 To dismantle existing wardrobe in 3 bedrooms $350

3 Design, fabricate & install cantilevered type of TV console/feature wall (6 ft) **** area. $1920

4 Design, fabricate & install cantiliver type of TV console/feature wall (4 ft) at master bedroom. $1280

5 Supply labour & material to install 4 units of classic door c/w complete iron mongeries at 3 bedrooms & store. (exclude door frame)

$800

6 Supply labour & material to install 1 set of 1/2hr fire rated door c/w complete iron mongeries at main entrance. (exclude door frame)

$1600

7 Supply labour & material to install 1 no. of casement tempered glass door at kitchen entrance. $700

Total Renovation Cost = $24388

 

Share this post


Link to post
Share on other sites

Dear Friend,

I would strongly suggest you to engage a sub-contractor for hacking. You will find one if you google.

They charge you 40% of what the contractors generally charge. Just let them know at front that they cannot damage the window grills, bathroom window glass grill and cannot damage the doors. Ask them to guarantee that they wont damage the cornices , false ceiling if any etc. Otherwise have to pay you.

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×