myorangeclam 0 Report post Posted September 13, 2011 Hi all, we've been having trouble getting approval from HDB to replace the full height windows at our point block resale flat. We have just been informed that there's a lengthy process, involving the BCA (Building & Construction Authority). Our renovation is otherwise almost completed, and we've replaced all our other casement windows, so this is really messing up our schedule. I would like to ask if anyone has gone through a similar process before, or if they know of any recent rule changes? Thanks in advance! Share this post Link to post Share on other sites
muffin 2 Report post Posted September 17, 2011 changing of full height windows seems to be a challenging task and they need time to access because it concern safety and can take up a lot of time, sometimes it cannot even be approved. Share this post Link to post Share on other sites