hock

Home In The West

Recommended Posts

Reno day 26

Tiling work 70% done. Only left with Mbr. Balcony tiles was ask to redo as step down was too high, and id came over to resolve. Heng ah.

Yesterday met up with aircon guy, will be installing a sys 4 for the bedrooms only, So no aircon for living. :(

This week, electrical guy coming to proceed with the work. Hope, finger cross, everything smooth smooth, no more hiccup, only left with 3 weeks to go.

Balcony tiles.

28555127.jpg

Close up

8b6c8d5c.jpg

See the west sun shining into the living room, no aircon, must be pretty hot hot hot.

63b797d7.jpg

Shot from balcony to living room

ccbe4c86.jpg

Edited by hock
 

Share this post


Link to post
Share on other sites

Join 46,923 satisfied homeowners who used renotalk quotation service to find interior designers. Get an estimated quotation

Congrats, things are looking good in your renovation. 3 more weeks, all stress would be over.

 

Share this post


Link to post
Share on other sites

Congrats, things are looking good in your renovation. 3 more weeks, all stress would be over.

hopefully, finger cross

 

Share this post


Link to post
Share on other sites

Reno day 33

Some mistake encounter so far:

1) Water tap at balcomy for my fish tank, told the contractor to drill nearer to the side of the balcony wall but end up they drill at the center, and route a horizontal pipe across.. haizzz... :( luckily ID resolve this pretty quick.

d6560ee8.jpg

2) washing machine water outlet install at the center, which took up the space of my WM, end up not enuf space to house the WM... currently still pending rectification. hope this could resolve fast.

e5566e90.jpg

L box done in living room

8420204a.jpg

be0e33d3.jpg

 

Share this post


Link to post
Share on other sites

Cont....

Partition work mostly up

bedroom 2

f37dd7b8.jpg

bedroom 3

IMG_2178.jpg

MBR

af60173d.jpg

Piping works

964f9645.jpg

MBR Balcony Tiles up.

d50d4952.jpg

This week painter coming. Color choosen. All white except for 2 bedroom.

 

Share this post


Link to post
Share on other sites

recently check with open net, previous owner did not sign up for the free installation which were done in early 2011. now i have to pay for the installation and waiting q is till end Nov 2011.... such a long wait and i cant hide cable trunking by then.

 

Share this post


Link to post
Share on other sites

Reno progress looking good my fren.

The truncking for the optic-fibre wire is slimmer than normal electrical wires trunkings. May not turn out as bad as u tink. ;)

Edited by stardust205
 

Share this post


Link to post
Share on other sites

No choice lah nw. Have to pay n showcase the trunking.

Reno progress looking good my fren.

The truncking for the optic-fibre wire is slimmer than normal electrical wires trunkings. May not turn out as bad as u tink. ;)

 

Share this post


Link to post
Share on other sites

Some of purchase that was deliver and install.

Ariston heater

1133d6b5.jpg

Ellane hood n hod

1070a0eb.jpg

Ixiss rain shower

4cbcede1.jpg

Lighting and toilet barang barang

132299f1.jpg

Edited by hock
 

Share this post


Link to post
Share on other sites

Went up to my unit in the evening and found the west sun so strong that it reach 3/4 of my living room. Think got to install those roller blind, black out type. Any recommendation?

71c43d3b.jpg

Edited by hock
 

Share this post


Link to post
Share on other sites

Reno day 41.

Counting down to end of august. Went up see see look look. Carpenter was working on kitchen cabinet as promise this week. Met contractor for granite top who came over to took some measurement. Electrician also busy installing lights n except for some loose socket point outstanding.. Window grill and glass door up too. Went down to kong tai to exchange ceiling fans as I feel my unit height seem short. Exchange 2 kdk baby fan instead. No choice.

Some photos update.

Kitchen cabinets half way done

f3123ad9.jpg

174a8941.jpg

Sink in place

e05663f9.jpg

Living room lightings

375e6216.jpg

 

Share this post


Link to post
Share on other sites

Yesterday went to check out the installation of bathroom accessories and meet up id. All items were installed. Only the towel rack in Mbr bathroom need to reinstall as it was too high for my wifey. Tiles need to change out after redo. Id ok with it and I feel very pai say, cause it's me who told the plumber to install at that height. Never think hard enuf. Next abit regret doing the box up of my Mbr bathroom pipes. After installation of the toilet bowl than realize my poo poo space very squeeze. No choice, have to bare with it. Can't put on any more weight, if not no room for poo poo.

Few photos to update.

Mbr bathroom. See the space for poo poo.

c047422a.jpg

c81660cb.jpg

Common bathroom

b5c7184b.jpg

Kitchen granite stone installed. Luv the white and clean feel.

c7aa3709.jpg

eeabb344.jpg

That's all for today. Counting down to 6 sept that is our move in date. Next week painter and carpenter will finish up remaining work and id will be arranging for chemical wash.

Edited by hock
 

Share this post


Link to post
Share on other sites

My MBR wc is just like urs, in between boxup wall and vanity cabinet, also no space for toilet roll holder at the side of wc. In the end, we place the toilet roll holder infront of the wc, better that taking the risk of a twisted back.. Haha...

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×