Recommended Posts

Looking for good contractors? Click here for your request

Had a discussion with my ID last night to confirm on the internal of wardrobe as well as kitchen and the recess area by the living area.

Realized painting started .. present installed too... haa ...

Next week lightings will be up.

Next wed laminates will be done.

Following week carpentry will be installed ... :)

Seems still on schedule ... ;)

 

Share this post


Link to post
Share on other sites

hi joyousonline,

mine smaller than urs, so renovation will be faster.. :P

but urs so much more spacious! looking fwd for your updates and progress.. :)

 

Share this post


Link to post
Share on other sites

Hi all i just got my keys for jade spring.

My ID quote for hacking wall $480, PE $500, supply labour & materials for floor touch up $800.

Is the above expensive???

Anyone can share how much they paid for hacking wall + PE + floor touch up?

Thks.

 

Share this post


Link to post
Share on other sites

if all in all is $800, sounds normal. if solely floor touch up (which i presume is make good the wall) requires $800, its ex.

But of coz, if the touching up is alot more work (such as close one opening, open another entrance etc ) then might be ?? hmm..

Mine PE $500...

hack and make good the wall $260 ...

but mine only half-wall.

 

Share this post


Link to post
Share on other sites
Hi Jade Spring member ,

Need help for site plan for FSM . Please PM me at sz_zps@yahoo.com.sg thank alot

Hi Sherlyn,

what site plan are you referring to?

If floor plan, its on the first page in which you will have it too.

:)

 

Share this post


Link to post
Share on other sites

Abit lazy to update, plus no one reads or comment. :(

But still, since start, shall update one or two photos of the progress ba.

Day 29 (29 Mar): Light be!

Pretty cove light (its warm light yet don't look overly warm. Just nice)

reno_as_of_20110330_lights008.jpg

They delivered my laminates as well. So that wednesday can get it up. :)

Zebrano, Supreme...

reno_as_of_20110330001.jpg

reno_as_of_20110330002.jpg

Day 30 (30 Mar): Laminates up!

photos are grainy as taken at night using iphone. :P

reno_as_of_20110331002.jpg

The separator ..

From here, the laminates looks darker. Love it!

reno_as_of_20110331003.jpg

 

Share this post


Link to post
Share on other sites

oh. in this case, the separator is at the door? separates from the homogenous tiles?

by the way, how much is the haulage fees charged by HDB? 1 of the ID we met told me it's abt $950??

Edited by chrissyyeo
 

Share this post


Link to post
Share on other sites

Just receive sms that service yard can have 3-track windows! Yeah!

Previously was only able to do a two-track as the top and bottom width is different.

2-track would means at any time, half-of-windows will be covered, which means reduced airflow.

But now means only 1/3 is covered which is acceptable.

Also, as my Id say, having a window in a way make the service yard part of the house, and helps to prevent rain from coming in.

(My kitchen faces the carpark, thus in a way no blockage, thus higher chance of rain comes in)

:)

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×