Jump to content
Find Professionals    Deals    Get Quotations   Portfolios
Sign in to follow this  
pixie

Our 711 House

Recommended Posts


Join 46,923 satisfied homeowners who used renotalk quotation service to find interior designers. Get an estimated quotation
Eh none...

Why u wan his pic?

Cos he bery handchum guy lor…:D :D

PS: your tblog link points to a nonexistent page.

Edited by neubie
 

Share this post


Link to post
Share on other sites
Hi there!

I like your floor plan! Mind sharing which block is this in BB? I just bought a 4A in BB too around blks 180+! :)

Mine is 117 which coincides with our wedding anniversary Nov 7th! hehe. the one bside CC.

Thanks!! =)

 

Share this post


Link to post
Share on other sites
Cos he bery handchum guy lor…:D :D

PS: your tblog link points to a nonexistent page.

Hmm hahaha.. okie i shall ask for IT-hubby help. =X

 

Share this post


Link to post
Share on other sites
wao..very fast work.. and nice choice of colour tiles.

cant wait to see more!

Thanks! Actually quite slow cos he was rushing another flat for CNY. My friend's who started 2 weeks after me, is right on par with me. LOL.

And there will be 3 weeks of break. =( Too anxious to see more!

But, good that he only has this regular group of guys to do. So unlike of larger firm where ID draws draws and "subcontracts" to a large group of uncontrolled QA team. So, I am happy to just wait for the "old birds" to come in.

Aircon installation in progress!! hehe ^^

Thanks! We wanted the tiles to be in living room but Alan said it would be not nice in such a large surface area, so i gotten it for 2 common rooms. MBR has a similiar pattern but slightly darker brown tiles. Hubby likes that, but I love this. So i get to have 2 rooms of it, and he has it in MBR. Smaller but i see it every night! grrr....

 

Share this post


Link to post
Share on other sites

Day 1 - 20th December: Hacking Day 1

Day 4 - 23rd December: Loading debris to truck.

Day 5 - 24th December: Loaded materials (cement, sand, tiles)

Day 8 - 27th December: Filling up the walls with cement before tiling

Day 10 - 29th December: Completed filling up of 2 toilets, kitchen and balcony walls.

Day 12 - 31st December: Tiled Kitchen (half) and Common Toilet

Day 17 - 5th January: Completed Tiling for Kitchen, Common Toilet, MBR Toilet. Started Living Room tilings

Day 18 - 6th January: Completed Rooms and almost there for living room. Felt the lines for our tiles are beautifully matched.

Day 21 - 9th January: Completed cement walkway @ entrance

Day 32 - 18th January: Completed aircon (with huge trunking!) , started electrical points

5380460101_f1a085e086.jpg

Day 33 - 19th January: Continued electrical points and more sockets!

5380461139_5be0455a26.jpg

Day 36 - 22nd January: Completed false ceilings. Where to get the lights?!

5380461535_d480a3095c.jpg

House is shaping up soon =)

Last week before CNY break...

Will be painting and putting up the platform ;)

 

Share this post


Link to post
Share on other sites

Thanks for the kind words.

Cant move in before CNY wor. =(

Has to wait till after CNY.

This week will be painting and platform week!!

After CNY will need to grab the hob, fridge, washing machine etc etc.

 

Share this post


Link to post
Share on other sites

Day 1 - 20th December: Hacking Day 1

Day 4 - 23rd December: Loading debris to truck.

Day 5 - 24th December: Loaded materials (cement, sand, tiles)

Day 8 - 27th December: Filling up the walls with cement before tiling

Day 10 - 29th December: Completed filling up of 2 toilets, kitchen and balcony walls.

Day 12 - 31st December: Tiled Kitchen (half) and Common Toilet

Day 17 - 5th January: Completed Tiling for Kitchen, Common Toilet, MBR Toilet. Started Living Room tilings

Day 18 - 6th January: Completed Rooms and almost there for living room. Felt the lines for our tiles are beautifully matched.

Day 21 - 9th January: Completed cement walkway @ entrance

Day 32 - 18th January: Completed aircon (with huge trunking!) , started electrical points

Day 33 - 19th January: Continued electrical points and more sockets!

Day 36 - 22nd January: Completed false ceilings. Where to get the lights?!

Day 41 - 27th January: Completed painting. Setting up parquet platform before closes for CNY

 

Share this post


Link to post
Share on other sites

Day 1 - 20th December: Hacking Day 1

Day 4 - 23rd December: Loading debris to truck.

Day 5 - 24th December: Loaded materials (cement, sand, tiles)

Day 8 - 27th December: Filling up the walls with cement before tiling

Day 10 - 29th December: Completed filling up of 2 toilets, kitchen and balcony walls.

Day 12 - 31st December: Tiled Kitchen (half) and Common Toilet

Day 17 - 5th January: Completed Tiling for Kitchen, Common Toilet, MBR Toilet. Started Living Room tilings

Day 18 - 6th January: Completed Rooms and almost there for living room. Felt the lines for our tiles are beautifully matched.

Day 21 - 9th January: Completed cement walkway @ entrance

Day 32 - 18th January: Completed aircon (with huge trunking!) , started electrical points

Day 33 - 19th January: Continued electrical points and more sockets!

Day 36 - 22nd January: Completed false ceilings. Where to get the lights?!

Day 41 - 27th January: Completed painting. Setting up parquet platform before closes for CNY

5400691135_7301b30943.jpg

Day 44 - 30th January: Completed platform. Polish after CNY

5400691137_c37c619572.jpg

 

Share this post


Link to post
Share on other sites
5400691135_7301b30943.jpg

whole house parquet? .. :unsure: below parquet got tile ?

Nope only part of my livinng room is parquet. no budget.. lol..

But yes, below parquet has tile =)

when is urs starting?

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×