thirdrockdweller 0 Report post Posted April 13, 2010 (edited) Reno Day +18 (11-04-2010) More updates, more pics. Kitchen wall rebuilt A view of inside the kitchen Yet another view. Kinda difficult to convey the sense of spaciousness the kitchen has at the moment with a photograph. Don't think my photography is doing a good job at establishing a sense of scale. Anyway, once the cabinets and appliances are in, bye bye space, hello clutter. Edited May 11, 2010 by thirdrockdweller Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 13, 2010 Reno Day +18 (11-04-2010) Marble tiles that will be eventually used for the MBR toilet (Curiously, not sure why there are so many pieces here for a really tiny toilet) A close up of the marble (Again, sorry about the condition of the lighting. Flash photography kills details ) Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 13, 2010 Reno Day +18 (11-04-2010) MBR toilet - Door frame hacked. This is to accomodate a swing door. Wall and floor tiling for guest toilet done Another view Share this post Link to post Share on other sites
samgalz 2 Report post Posted April 13, 2010 coming up nicely! the toilet is swee swee! Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 13, 2010 coming up nicely! the toilet is swee swee! Thank you thank you First appointment soon I see. Must be excited! Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 13, 2010 Aircon piping/trunking is up. Pics coming soon. Share this post Link to post Share on other sites
samgalz 2 Report post Posted April 13, 2010 Thank you thank you First appointment soon I see. Must be excited! yeah!! can't wait..am counting down to it. Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 13, 2010 Reno Day +20 (13-04-2010) Aircon trunking completed; MBR Guest Room/Baby Room Study Dining/Living Area Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 13, 2010 Reno Day +20 (13-04-2010) False ceiling in progress; Living room Another view Share this post Link to post Share on other sites
leechaorui 2 Report post Posted April 14, 2010 Very nice reno and very clever design as shown in your 3D pictures. Kudos to you, thirdrockdweller. Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 14, 2010 Very nice reno and very clever design as shown in your 3D pictures. Kudos to you, thirdrockdweller. Thank you thank you Share this post Link to post Share on other sites
mango88 0 Report post Posted April 14, 2010 hi, very nice 3D design you have came up!!! Pei fu..Pei fu mind to share which ID firm did you went? thank you so much Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 14, 2010 (edited) hi, very nice 3D design you have came up!!! Pei fu..Pei fu mind to share which ID firm did you went? thank you so much Hi mango88, Our ID is; I.D.+A 237 Alexandra Road, The Alexcier #07-02 Singapore 159929 +65 64796566 Ask for Frank Tang and their associated contractor is; Growth Builder Pte Ltd (same contact as above) Ask for Choo Man Wai Great and very creative ID. On the contractor side of things, solid workmanship and Mr. Choo is very meticulous. Edited June 12, 2010 by thirdrockdweller Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 14, 2010 (edited) Reno Day +18 (11-04-2010) Marble tiles that will be eventually used for the MBR toilet (Curiously, not sure why there are so many pieces here for a really tiny toilet) Ah, mystery solved. Asked my contractor about this. Our very nice contractor brought a truck load of marble tiles (more in the MBR) and had them all splayed out on the floor. Was wondering why there was so many. Clearly our tiny toilet didn't need that many. As he explained it, he had all tiles laid out so that he could pick, match and tag the tiles that will be eventually used. This was to ensure aesthetic consistency. He will haul the remaining tiles back. Wah, this is how the professionals do it. Very very detailed and methodical. :good: Edited May 11, 2010 by thirdrockdweller Share this post Link to post Share on other sites
thirdrockdweller 0 Report post Posted April 16, 2010 (edited) Reno Day +23 (16-04-2010) False Ceiling, False Ceiling, False Ceiling Living room false ceiling is done! Kitchen false ceiling, checked! Passageway false ceiling, up! Another view (Towards the MBR) Edited May 11, 2010 by thirdrockdweller Share this post Link to post Share on other sites