mohashar 0 Report post Posted September 29, 2009 Hi, I just got the quotation $1700 from one of the contractor to renovate two tolilets i.e., overlaying the flooring tiles only.(Overlay + only floor) Is this resonable? Share this post Link to post Share on other sites
jadens28 1 Report post Posted September 29, 2009 Hi, I just got the quotation $1700 from one of the contractor to renovate two tolilets i.e., overlaying the flooring tiles only.(Overlay + only floor) Is this resonable? it is over quota. the most is ard 1.2k ba, if u only do that. Share this post Link to post Share on other sites
mohashar 0 Report post Posted September 29, 2009 Master Bed room : 1. Flooring - 500 2. Shower Kerb - 120 3. Labour charge - Dismantle and reinstall W.C and wash basing - 210 Common Bed room: 1. Flooring - 450 2. Labour charge - Dismantle and reinstall W.C and wash basing - 210 3. To supply and install one power point - 120 Total $ 1,660 Is it still high? Share this post Link to post Share on other sites
jaskel 2 Report post Posted September 29, 2009 Master Bed room : 1. Flooring - 500 2. Shower Kerb - 120 3. Labour charge - Dismantle and reinstall W.C and wash basing - 210 Common Bed room: 1. Flooring - 450 2. Labour charge - Dismantle and reinstall W.C and wash basing - 210 3. To supply and install one power point - 120 Total $ 1,660 Is it still high? For this small project, I think is reasonable for the pricing. Share this post Link to post Share on other sites
adrian01 0 Report post Posted October 6, 2009 Master Bed room : 1. Flooring - 500 2. Shower Kerb - 120 3. Labour charge - Dismantle and reinstall W.C and wash basing - 210 Common Bed room: 1. Flooring - 450 2. Labour charge - Dismantle and reinstall W.C and wash basing - 210 3. To supply and install one power point - 120 Total $ 1,660 Is it still high? Does it include the toilet accessories? Share this post Link to post Share on other sites