red_devil 0 Report post Posted August 25, 2009 red devil, do you have the code # for the defected kitchen floor tiles? I think is VT3639.... Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-Aug-2009 -updates kitchen and balcony floor tiles completed. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-Aug-2009 -updates Common toilet window for the first floor was relocated. Just a slight relocation of position. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25 August 2009 Balcony windows are up. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-August 2009 Living room and dining room tiles are almost done. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-August-2009 Second floor common toilet's window relocated. Slight shift of location. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-August-2009 Routing wires over the top for lightings for common toilet - first floor . Water pipes... Drawing by Jason on the tiles on the layout Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-August-2009 MBR toilet - Window relocated also. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 25, 2009 25-August-2009 Piping for MBR toilets. That all for today. Share this post Link to post Share on other sites
beany0811 1 Report post Posted August 25, 2009 pipings r very nicely laid. the change of window fm 2 panels to 1 panel also made it look nicer. everytime i see the different bathrooms wip, i regret not choosing more varied tiles for the bathrooms but... nice choice u have there Share this post Link to post Share on other sites
HomeMaster 0 Report post Posted August 26, 2009 Remember to put a ventilation fan in the toilet.... Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 26, 2009 pipings r very nicely laid. the change of window fm 2 panels to 1 panel also made it look nicer. everytime i see the different bathrooms wip, i regret not choosing more varied tiles for the bathrooms but... nice choice u have there Hi beany, thanks. My wife choose the tiles. Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 26, 2009 Remember to put a ventilation fan in the toilet.... Oh...we are not installing... I hope we don't faint inside.... Share this post Link to post Share on other sites
familyof4 0 Report post Posted August 26, 2009 Good progress leh Ben, How long more your reno gonna take? Share this post Link to post Share on other sites
red_devil 0 Report post Posted August 26, 2009 Good progress leh Ben, How long more your reno gonna take? I lost track! But, I think is last week of Sept I think. How are u doing? You seems stress these days leh. no more "leh" hor...Later your kids pop over and see..."Mummy", tell u cannot say leh...now u type "leh"..hehe Share this post Link to post Share on other sites