Which To Do First?

Recommended Posts

Hi All,

I have this question on my mind and been thinking through the night, but seems like i cannot get the sequence correct.

Pardon my question if it sounds stupid. I am going to collect my key in 1 mth's time, its a resales condo so I am thinking of painting the walls, polish the floors, and change the aircon system. This is the immediate plan tat I have on mind. Subsequently, I will do the carpentry works on the living room, kitchen (maybe) and master bed room.

How should the sequence goes in order not to disrupt the uncompleted tasks, or rather, so tat the completed tasks will not be affected. I am doing my renovation in around 3 tranches since I won't move in soo soon as we will move in only after our wedding which is next year.

Thanks.

Cheers,

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Hi Ling Er,

I can share with you my flow

Hacking - > Painting& Plastering -> Air Con -> Carpentry

Usually carpentry is last as once everything is done, they just fix and install.

Dont worry, once you engage a contractor, he will go through with you the sequence.

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×