Bon07

Is 30k Possible For A 5rm Flat?

Recommended Posts

Hi everyone,

we are doing the kitchen cabinets, 2 toilets (tiles included), master bedroom with walk-in wardrobe, Tv console and feature wall, bombshelter feature wall and a 5ft hull ht shoe cabinet....is 30 k enuff?

anyway received the following quote....reasonable?

A Demolition Works

1 Labour to dismantle existing shoes cabinet & divider at foyer area 150

2 Labour to dismantle existing kitchen cabinet 200

3 Labour to dismantle existing wardrobe at master bedroom 140

4 Labour to dismantle existing storage cabinet at master bedroom area -

5 Labour to dismantle existing toilet bowl, vanity and bath accessories at 2 bedrooms 105

6 Labour to hack off existing wall and floor tiles at master bedroom 425

7 Labour to hack off existing wall and floor tiles at common bedroom 280

8 Labour to dismantle existing doors at 2 bedrooms ???

9 Labour to clear debris off site ???

Sub-total 1,300

B Foyer and Shelter Area

1 To design and install (est L6.5ft) full ht shoe cabinet with backing using solid-ply laminate/veneer finishing 2,110

2 To design and instal (est L4.5ft) ful ht box-up using solid-ply laminate/veneer finishing c/w tic-tac door at shelter area 900

3,010

C Living Hall Area

1 To design and install (est L9ft) TV console w/ drawer unit using solid-ply laminate/veneer finishing 1,260

2 To design and install (est L9ft) full ht feature wall using solid-ply laminate/veneer finishing at console area 1,800

3 To supply grinding and varnish existing platform parquet flooring 100

3,160

D Kitchen Area

1 To construct 50mm height concrete kitchen cabinet base, washing machine base c/w tiles finishes 180

2 To design and install (est L3ft) full ht kitchen storage cabinet using solid-ply laminate finishing with Blum Hinges 4,880

3 To design and install (est L19.5ft) bottom kitchen cabinet using solid-ply laminate finishing with Blum Hinges

4 To design and install (est L13ft) top kitchen cabinet using solid-ply laminate finishing with Blum Hinges

* ABS door trimming for all door edges

* Internal polygon finishing

* Blum drawer runner system- 1set

* Sand blasted glass door at dish drainer area

* Stainless steel dish drainer

* Installation (only) for hood,hob

5 To supply and install (est L13ft) tempered colored glass backing in between top & bottom cabinet area 700

6 To supply and install (est L19.5ft) solid black galaxy granite top 2,250

7 To supply and box up existing sewerage piping using solid-ply laminate finishing ???

8 To install 1 no. of kitcehn sink and tap c/w drainage system 120

9 To install 1 no. of washing machine tap c/w mini-valve, in/outlet drainage system 80

10 Kitchen stainless steel piping 250

8,460

E Common Bathroom

1 To supply and overlay ceramic/homogeneous floor tiles (non-slip) 420

2 To supply and overlay ceramic/homogeneous wall tiles 1,350

3 To supply and apply waterproofing using prepack 3-1 ultra hard quick seal membrane at wet area

4 To construct 50mm height shower kerb FOC

5 To install 1 no.of sit toilet bowl 110

6 To install 1 no. of wash basin 80

7 To install 1 no. of mixer tap c/w shower set 50

8 To install 1 no of sprayjet c/w mini valve 40

9 To install 2 sets of toilet accessories FOC

10 To install 1 no. of central heater c/w heater wire 80

11 To lay 1 no. of hot water pipe at the shower area 290

12 To install PD door 300

2,720

F Master Bedroom

1 To supply and install (est L8ft) full ht false wall divider using plaster board partition finishing at walk-in wardrobe area 380

2 To design and install (est L14ft) full ht walk-in wardrobe w/o doors using coloured PVC 2,930

3 To design and install (est L2ft) low ht storage cabinet using solid-ply laminate/veneer finishing at walk-in area

4 To supply and install (est L3ft) full ht sliding door using top-hung track mechanism with mirror 880

5 Labor & material to install mirror at walk-in-wardrobe area.(700x2100)mm 250

6 To supply and install 1 nos. of (est L3ft) full ht tinted mirror at left bed side area 380

7 To design and install (est L5ft) half ht headboard using solid-ply laminate/veneer finishing w/ light box and sand blasted glass panel 480

8 To supply and lay selected wall paper design as bedhead feature wall finishing (KIV) -

9 To design and install 1 no. of queen size bed frame using solid-ply laminate/veneer finishing 950

10 To supply and lay full ht selected wall paper design as feature wall finishing (KIV) -

11 To design and install (est L3.5ft) full ht storage cabinet using solid-ply laminate/veneer finishing -

12 To supply grinding and varnish existing parquet flooring 260

6,510

G Master Bathroom

1 To supply and apply waterproofing using prepack 3-1 ultra hard quick seal membrane at wet area -

2 To supply and overlay ceramic/homogeneous floor tiles (non-slip) 470

3 To supply and overlay ceramic/homogeneous wall tiles 1,500

4 To construct partial concrete wall using 63mm hollow block at shower area 200

5 To supply and install 1set of 10mm thick tempered glass shower enclosure with stainless steel handle 520

6 To design and install (est L3ft) vanity bottom cabinet using solid-ply laminate finishing 650

7 To supply and install (est L5.5ft) plywood mirror backing with light pelment

8 To supply and install (est L3ft) black galaxy Granite top 320

9 To supply and install 1 no. of 10mm thick tempered frosted casement glass door with stainless steel handle 550

10 To install 1 no.of sit toilet bowl 110

11 To install 1 no. of wash basin 80

12 To install 1 no. of mixer tap c/w shower set 130

13 To install 1 no of sprayjet c/w mini valve 40

14 To install 2 sets of toilet accessories FOC

15 To construct 50mm height shower kerb FOC

16 To lay 1 no. of hot water pipe at the shower area 290

4,860

H Bedroom 2

1 To supply grinding and varnish existing parquet flooring 260

2 To supply and install bedroom veneer skin door c/w standard locket 570

830

I Bedroom 3

1 To supply grinding and varnish existing parquet flooring 260

2 To supply and install bedroom veneer skin door c/w standard locket 570

830

J Painting and ceiling works

1 To supply and paint whole unit wall, ceiling,pipe and door frame using ICI/Nippon emulstion paint with 6 colors 1,500

2 To design and install false ceiling at master bedroom and walk-in area 580

2,080

K Miscellaneous works

1 Labour to provide haulage/uploading and downloading sand and cement 650

2 To supply and lay protection sheet at working area FOC

3 Labour to provide chemical and general washing upon completion FOC

4 HDB permit and document handling fees FOC

5 Labor & material to plaster whole house using plastering compound. ???

650

Grand Total 34,410

Edited by Bon07
 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

all in all, only reno the kitchen, 2 bathroom, bedroom and living room.

2 other bedrooms are left untouch except for painting and varnishing of parquet floor.

 

Share this post


Link to post
Share on other sites
Hi everyone,

we are doing the kitchen cabinets, 2 toilets (tiles included), master bedroom with walk-in wardrobe, Tv console and feature wall, bombshelter feature wall and a 5ft hull ht shoe cabinet....is 30 k enuff?

anyway received the following quote....reasonable?

A Demolition Works

1 Labour to dismantle existing shoes cabinet & divider at foyer area 150

2 Labour to dismantle existing kitchen cabinet 200

3 Labour to dismantle existing wardrobe at master bedroom 140

4 Labour to dismantle existing storage cabinet at master bedroom area -

5 Labour to dismantle existing toilet bowl, vanity and bath accessories at 2 bedrooms 105

6 Labour to hack off existing wall and floor tiles at master bedroom 425

7 Labour to hack off existing wall and floor tiles at common bedroom 280

8 Labour to dismantle existing doors at 2 bedrooms ???

9 Labour to clear debris off site ???

Sub-total 1,300

B Foyer and Shelter Area

1 To design and install (est L6.5ft) full ht shoe cabinet with backing using solid-ply laminate/veneer finishing 2,110

2 To design and instal (est L4.5ft) ful ht box-up using solid-ply laminate/veneer finishing c/w tic-tac door at shelter area 900

3,010

C Living Hall Area

1 To design and install (est L9ft) TV console w/ drawer unit using solid-ply laminate/veneer finishing 1,260

2 To design and install (est L9ft) full ht feature wall using solid-ply laminate/veneer finishing at console area 1,800

3 To supply grinding and varnish existing platform parquet flooring 100

3,160

D Kitchen Area

1 To construct 50mm height concrete kitchen cabinet base, washing machine base c/w tiles finishes 180

2 To design and install (est L3ft) full ht kitchen storage cabinet using solid-ply laminate finishing with Blum Hinges 4,880

3 To design and install (est L19.5ft) bottom kitchen cabinet using solid-ply laminate finishing with Blum Hinges

4 To design and install (est L13ft) top kitchen cabinet using solid-ply laminate finishing with Blum Hinges

* ABS door trimming for all door edges

* Internal polygon finishing

* Blum drawer runner system- 1set

* Sand blasted glass door at dish drainer area

* Stainless steel dish drainer

* Installation (only) for hood,hob

5 To supply and install (est L13ft) tempered colored glass backing in between top & bottom cabinet area 700

6 To supply and install (est L19.5ft) solid black galaxy granite top 2,250

7 To supply and box up existing sewerage piping using solid-ply laminate finishing ???

8 To install 1 no. of kitcehn sink and tap c/w drainage system 120

9 To install 1 no. of washing machine tap c/w mini-valve, in/outlet drainage system 80

10 Kitchen stainless steel piping 250

8,460

E Common Bathroom

1 To supply and overlay ceramic/homogeneous floor tiles (non-slip) 420

2 To supply and overlay ceramic/homogeneous wall tiles 1,350

3 To supply and apply waterproofing using prepack 3-1 ultra hard quick seal membrane at wet area

4 To construct 50mm height shower kerb FOC

5 To install 1 no.of sit toilet bowl 110

6 To install 1 no. of wash basin 80

7 To install 1 no. of mixer tap c/w shower set 50

8 To install 1 no of sprayjet c/w mini valve 40

9 To install 2 sets of toilet accessories FOC

10 To install 1 no. of central heater c/w heater wire 80

11 To lay 1 no. of hot water pipe at the shower area 290

12 To install PD door 300

2,720

F Master Bedroom

1 To supply and install (est L8ft) full ht false wall divider using plaster board partition finishing at walk-in wardrobe area 380

2 To design and install (est L14ft) full ht walk-in wardrobe w/o doors using coloured PVC 2,930

3 To design and install (est L2ft) low ht storage cabinet using solid-ply laminate/veneer finishing at walk-in area

4 To supply and install (est L3ft) full ht sliding door using top-hung track mechanism with mirror 880

5 Labor & material to install mirror at walk-in-wardrobe area.(700x2100)mm 250

6 To supply and install 1 nos. of (est L3ft) full ht tinted mirror at left bed side area 380

7 To design and install (est L5ft) half ht headboard using solid-ply laminate/veneer finishing w/ light box and sand blasted glass panel 480

8 To supply and lay selected wall paper design as bedhead feature wall finishing (KIV) -

9 To design and install 1 no. of queen size bed frame using solid-ply laminate/veneer finishing 950

10 To supply and lay full ht selected wall paper design as feature wall finishing (KIV) -

11 To design and install (est L3.5ft) full ht storage cabinet using solid-ply laminate/veneer finishing -

12 To supply grinding and varnish existing parquet flooring 260

6,510

G Master Bathroom

1 To supply and apply waterproofing using prepack 3-1 ultra hard quick seal membrane at wet area -

2 To supply and overlay ceramic/homogeneous floor tiles (non-slip) 470

3 To supply and overlay ceramic/homogeneous wall tiles 1,500

4 To construct partial concrete wall using 63mm hollow block at shower area 200

5 To supply and install 1set of 10mm thick tempered glass shower enclosure with stainless steel handle 520

6 To design and install (est L3ft) vanity bottom cabinet using solid-ply laminate finishing 650

7 To supply and install (est L5.5ft) plywood mirror backing with light pelment

8 To supply and install (est L3ft) black galaxy Granite top 320

9 To supply and install 1 no. of 10mm thick tempered frosted casement glass door with stainless steel handle 550

10 To install 1 no.of sit toilet bowl 110

11 To install 1 no. of wash basin 80

12 To install 1 no. of mixer tap c/w shower set 130

13 To install 1 no of sprayjet c/w mini valve 40

14 To install 2 sets of toilet accessories FOC

15 To construct 50mm height shower kerb FOC

16 To lay 1 no. of hot water pipe at the shower area 290

4,860

H Bedroom 2

1 To supply grinding and varnish existing parquet flooring 260

2 To supply and install bedroom veneer skin door c/w standard locket 570

830

I Bedroom 3

1 To supply grinding and varnish existing parquet flooring 260

2 To supply and install bedroom veneer skin door c/w standard locket 570

830

J Painting and ceiling works

1 To supply and paint whole unit wall, ceiling,pipe and door frame using ICI/Nippon emulstion paint with 6 colors 1,500

2 To design and install false ceiling at master bedroom and walk-in area 580

2,080

K Miscellaneous works

1 Labour to provide haulage/uploading and downloading sand and cement 650

2 To supply and lay protection sheet at working area FOC

3 Labour to provide chemical and general washing upon completion FOC

4 HDB permit and document handling fees FOC

5 Labor & material to plaster whole house using plastering compound. ???

650

Grand Total 34,410

 

Share this post


Link to post
Share on other sites

Any wiring work (i.e. light points) and ceiling work (i.e. false ceiling, L-box), as it will be a substantial amount.

 

Share this post


Link to post
Share on other sites
Guest melancholic
Any wiring work (i.e. light points) and ceiling work (i.e. false ceiling, L-box), as it will be a substantial amount.

The carpentry work seems rather high. From my experience, you can bargain down quite a fair bit.

But seeing that you intend to do many things, $30k is definitely not enough.

If you are doing ceiling works (i.e. false ceilings and lightbox), that can easily set you back $1500 to $2500. Electrical works (extension of lighting points, switches etc.) can also set you back $1500 to $2500.

The ID that I intend to sign up tomorrow only charges $100 psf for kitchen cabinet (without the blum hinges). In fact, Classic Kitchen charges only about $103 psf for top cabinet and $120 psf for bottom (before GST) and they use hafale silent closing hinges and give you 3 Hettich V6 Quadro drawers.

 

Share this post


Link to post
Share on other sites
Any wiring work (i.e. light points) and ceiling work (i.e. false ceiling, L-box), as it will be a substantial amount.

ya, have wiring work and false ceiling in master bedroom and MBR toilet

 

Share this post


Link to post
Share on other sites
The carpentry work seems rather high. From my experience, you can bargain down quite a fair bit.

But seeing that you intend to do many things, $30k is definitely not enough.

If you are doing ceiling works (i.e. false ceilings and lightbox), that can easily set you back $1500 to $2500. Electrical works (extension of lighting points, switches etc.) can also set you back $1500 to $2500.

The ID that I intend to sign up tomorrow only charges $100 psf for kitchen cabinet (without the blum hinges). In fact, Classic Kitchen charges only about $103 psf for top cabinet and $120 psf for bottom (before GST) and they use hafale silent closing hinges and give you 3 Hettich V6 Quadro drawers.

wow, haven heard of hafale and Hettich V6 Quadro drawers....must be pretty high end

 

Share this post


Link to post
Share on other sites
Is carpentry the most expensive out of all? As in it takes up the most cost ya?

ya....carpentry for masterbedroom, kitchen, foyer and living room.

only tiling the 2 toilets

 

Share this post


Link to post
Share on other sites
ya....carpentry for masterbedroom, kitchen, foyer and living room.

only tiling the 2 toilets

Hey i hope you did not share our discussion

Edited by darkromeo
 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  


×