Have been renoing for amost 3 full weeks, but progress seems little...

Mine is 4A HDB, 90sqm. Reno starts on 20th Oct.

First week: remove laminated flooring and hacking toilet & kitchen (wall & floor)

2nd week until now (almost 3 week):

- Kitchen wall tiles finished.

- Common toilet wall tiles 95% finished

- Master toilet wall tile 80% finished.

- Store room flooring layed.

And that's all... Is it consider as normal? :dunno:

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

Is there work done everyday? U should consult ur contractor why izzit so slow... Got manpower issue? But

B4 any conclusion, u should visit ur flat every night to see any work done on tad specific day... Then u'll know if its slow anot... ^^

If he knows u r particular abt work done everyday, i think he'll "on the ball"...

Tis tips is useful for all layman who's renovating their hse...

 

Share this post


Link to post
Share on other sites

This is good idea.

Everyday i went down... some little work is done... But i feel for 3 ppl to do so little work in a day is a bit slow...

But I don't dare to push too much... later they hurry in work without paying much attention to quality...

:bangwall:

 

Share this post


Link to post
Share on other sites

normal progress takes abt 4-6weeks. I prefer tiling to be done carefully and slowly. If you're not in a hurry, and things are moving, then don't have to worry too much.

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×