Nice glass door!! May i know how much are u being charge for that?

Hi lushbelle,

Thanks :)...it so much better than the old door. As a package with the reno, I got it for $800 for a 12mm thick tempered glass. The glass guy is also doing me a favour by putting in frosted sticker strips for the door to prevent accidents for humans and my dog as well...he cannot do anything fancy, so just horizontal stripes which is fine....also includes the aluminium pelmet which is still not up yet.

 

Share this post


Link to post
Share on other sites

DAY 26

Works:

--Kitchen top cabinets up

--LG guy re-appointment

The top cabinets are finally up and its looking good :)

P1020516.jpg

P1020517.jpg

P1020527.jpg

Lower cabinet drawers - they have rectified to give me 2 deep drawers :good:

P1020533.jpg

Perhaps you can see the smooth glossy finish in the reflection

P1020529.jpg

I have to comment that all these while Ah Bee has been very friendly and willing to help out in the rectifications or adjustments...so I am definitely very pleased with his attitude and helpfulness, in view of my fussiness, and attention to details :good:

 

Share this post


Link to post
Share on other sites

DAY 26 cont

Sink cabinet cabinet rectified...cut out holes for the water pipe :good:

P1020536.jpg

Closer look

P1020537.jpg

From the top

P1020539.jpg

Heres the Rubine stainless steel sink L580 x W450 x D200mm, 1.2mm thickness.

Its the biggest single bowl to fit my cabinet. I have to maximise my sink space..so this one gives the biggest volume ( Bowl size is L540 x W410mm ), and more usable space than the rest.

Bought from Poh Joo at $290 (no gst )

P1020643.jpg

The LG guy came... and I gave him my requirements, paritcularly, the countertop must flushed with the inner edge of the sink..that is, zero reveal.

(Positive reveal means the sink edge showing, or negative reveal meaning the solid surface overhangs so the sink edge is covered and not exposed )

He said that there will be a min of 3- 5 mm allowance.. :unsure:

I gave him the paper cut out of the sink and ask to do the best he can.

So got to wait another week for the solid surface top to be ready.

 

Share this post


Link to post
Share on other sites

DAY 37

Works:

--Stainless steel backing up

The stainless steel backing is installed.

P1020578.jpg

Its 0.9mm thickness....

P1020589.jpg

A cursory look at the workmanship ( do note its not cleaned up yet...theres dust and glue around ):

Closeup of the laminate joints

P1020606.jpg

Even gaps, straight lines

P1020592.jpg

Closeup of sink cabinet corner - as 1mm thick laminate is used, Ah Bee took the initiative to touchd up the corner joint to enhance the looks :good: ,otherwise a dark line would show.

P1020609.jpg

 

Share this post


Link to post
Share on other sites

DAY 37 cont

The 1 mm thick ABS trimming --makes it look even better than the std 2 mm ones, and comes in matching colours too

P1020597.jpg

Blum hinges and blumotion clip installed

P1020612.jpg

Price is $2.30 for hinge, $2.50 for the clip on blumotion, sold separately..

I used the BLUM 500mm full extension runners, and it costs $47.89 each set...7% GST not included yet in the prices.

BLUM prices are controlled, unless you are getting " a lot", you may get a discount.

Coming back to LG, the manager in charge and his 2 executives came, that was about 5 days ago...this is the 3rd time that LG people had to come for measurements. I was wondering if it was so difficult to get a zero reveal for the sink?? :dunno: and feel a bit pai say...maybe the other clients just leave it to them to do with no particular requests?

Nevertheless, the manager was very nice and friendly. He took careful measurements, and said he will try his best to give a zero reveal for my sink, but give an allowance of maybe 1 mm...ok, thats acceptable. I had some queries and this is what I found out about LG solid surface top:

1. Very high acrylic content, so stronger and more durable unlike the cheaper higher polyester content ones.

2. Non porous surface, so stains will not seep through

3. Antimicrobial -- use by a lot of food outlets,.. even better than granite

4. Fire rating class 1 -- will not burn

5. Will not yellow or discolour-- thats what I wanted to hear :) for my white top

6. Heat resistant

7. Chemical resistant

8. Can be polished to look new again... costs about $20 pfr

9. Can be repaired

10. Seamless

So after they left, I was thinking my solid surface should be perfect :)

 

Share this post


Link to post
Share on other sites
DAY 37 cont

The 1 mm thick ABS trimming --makes it look even better than the std 2 mm ones, and comes in matching colours too

P1020597.jpg

Blum hinges and blumotion clip installed

P1020612.jpg

WOW u have a very nice Kitchen cabinet!!! :dancingqueen:

 

Share this post


Link to post
Share on other sites

DAY 38

Works:

--Installation of LG Hi Macs solid surface

Finally after almost 2 weeks of waiting, my solid surface is ready for installation..the rest of the contractors are on hold till the top is installed.

It came in 2 pieces...

Fitting the pieces

P1020620.jpg

P1020621.jpg

Space between the 2 pieces, and the hobs' cut out

P1020623.jpg

Sink cut out

P1020624.jpg

The sink was taken away by the LG people after the manager's visit...so its the 4th time they came in total :jawdrop:

However they forgot to send the sink together with the top, the guy called up and was told to wait for the sink to be rush over in an hour's time :bangwall: , you can see the workers whiling away in the yard area...

Opportunity to take more pics :notti:

 

Share this post


Link to post
Share on other sites

DAY 38 cont

The sink cut out wasnt aligned properly to the cut out on inspection, it was 5 mm off position to the back.

Back portion..showing wood underneath

P1020638.jpg

Front portion, top overhanging the wood

P1020640.jpg

That means my sink position needs to be shifted backwards...after all the measurements :unsure:

The sink finally arrived, and the workers are back to work.

Trimming the wood to fit the sink into its new position

P1020644.jpg

Drilling the hole for the mixer tap

P1020646.jpg

Applying the silicone on the sink

P1020650.jpg

Edited by oogachaga
 

Share this post


Link to post
Share on other sites

DAY 38 cont

Then the solid surfaces were clamped to hold it steady, so that the gap can be filled with the joint adhesive. See the plastic bag in front to collect the overflow.

P1020656.jpg

then the excess silicone was scraped from the sink

P1020658.jpg

Trimming and polishing was done after setting of the joint adhesive.

Final result -- zero reveal of the sink accomplished :thumbs up:

P1020670.jpg

P1020672.jpg

P1020676.jpg

Edited by oogachaga
 

Share this post


Link to post
Share on other sites
wah. so nicely done.

show the pics of the join at the solid top. how come need to join? cannot one piece?

Hi mwerkz,

Will be continued in the next chapter :)

I understand that it comes in 6 ft slabs, anything bigger will require joining.

 

Share this post


Link to post
Share on other sites

DAY 43

Works:

--Everybody coming together..electricians, painters, plumbers, carpenter to finish up

Now for the LG solid surface, lets see the profile of the backsplash and the very neat and nicely done siliconing the LG guy has done..must give credit where its due :thumbs up:

P1020686.jpg

P1020687.jpg

however, the supposedly seamless joint cannot escape my eagle eyes :notti:

P1020681.jpg

P1020685.jpg

I highlighted to Henry, and he will be getting the LG guy to rectify...apparently they worked overtime that day because wasted an hour waiting for the sink to be delivered.

Edited by oogachaga
 

Share this post


Link to post
Share on other sites

DAY 43 cont

Painting:

- replaster cracks on walls

- repair spawling concrete on ceiling and master bedroom bay window

- painting door and door frames using Nippon Bodelac 9000

- yard and kitchen using Nippon Teflon paint

- patch up holes in ceiling after lighting installed

Bedroom door painted - one of the painters

P1020703.jpg

Common toilet door frame painted..also switches replaced

P1020704.jpg

Electrical:

- replace switches

- install lightings

- connecting the kitchen appliances...oven, hood, dishwasher and induction hob

Switch and socket installed

P1020723.jpg

Before - lights in dining area. Thats Henry in the kitchen having a discussion with Tek, and plumber

P1020708.jpg

After - new track lighting, using the Legrand Mallia dimmer

P1020725.jpg

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×