gaiusparx 0 Report post Posted September 7, 2008 Doing the following reno for my resale flat, pls advice the best sequence to carry out the reno: a. painting walls b. redo whole kitchen c. shift and move electrical wiring d. replace existing 3+1 aircons Should I do the painting last? Share this post Link to post Share on other sites
ryan13680 0 Report post Posted September 7, 2008 I think it is this order: Kitchen (Hacking, Tiling, Piping) Electrical Replace Aircons Painting Kitchen (Cabinets) Share this post Link to post Share on other sites
gaiusparx 0 Report post Posted September 7, 2008 Never thought of splitting the kitchen cabinet. I think I will follow this. Thanks Share this post Link to post Share on other sites