johnhome 0 Report post Posted December 21, 2007 anyone with input on this?1) Electrical/audio cable /phone2) air con trunking3) hacking of toilet/ tiling of toilet4) painting first OR cabinet first?anyone with template for sequence of events for reno as i need advice as i m engaging contractor direct.also, any advice on what to look for out, what to be aware of?how to pinpoint who borke my floor tiles from some heavy object (eg hammer doprop on floor)etc Share this post Link to post Share on other sites
joe_ling 0 Report post Posted January 9, 2008 1st step flooring have to be done first2nd step electrical works for whole house3rd step false ceiling / L-box (if you're doing it)4th step painting of whole house (3 coating)5th step aircon trunking & aircon unit6th step carpentry7th step painting again (final touch up)8th step final clean up & wahing up9th step Final Inspection10th step Turn Key Session & handover warranty cert. Share this post Link to post Share on other sites
joe_ling 0 Report post Posted January 21, 2008 Before the renovation or even anything starts, please go down to the premises with the ID / Contractor that you've hired to go thru the place with you together with a notebook in hand & a camera, please take down the pictures & write down where certain cracks or what nots that are already on the wall & all defaults / defects in the house.Pictures have to be taken before, during & after the process of hacking & demolition as proof. Pictures must also be taken during the waterproofing of the kitchen & bathroomDo go thru all contracts terms & conditions before you sign on the dotted line. Check, check, check & double check at all times. Make sure the ID / contractor does goes down on site to supervised the job site and the workers. No short cuts allowed The ID / contractor must paste the notice of renovation at the lift lobby of the void deck between the lifts, at the lift lobby level where you're residing. They must also inform the neighbours that are residing on your left & right side (2 units), downstairs & upstairs as well (2 units) to inform them of the inconvenience caused.Try to work within monday - friday 9am - 5pm only. Saturday the most is before 1pm and no hacking or knocking is allowed on weekends. Observed all rules & regulations from HDB.That's all folks. Share this post Link to post Share on other sites