Renovation Sequence

Recommended Posts

hi, i will be doing some minor renovation to my resale flat. Below are the following things to be done :

1. re-tiling for the 2 toilets wall and floor + WC +toilet fixtures (done by reno contractor)

2.painting for the whole house (DIY)

3.dismantling and installation of new aircon sys3 in 3 bedrooms (aircon vendor)

4.installation of lights for the whole house (done by reno contractor)

5.delivery of electrical app like wm,fridge...etc

6.delivery of furnitures like sofa,table,bed+mattress

7.chemical wash for whole house (done by reno contractor)

Anyone can advice the sequence for the above mentioned?

Thanks a lot!

 

Share this post


Link to post
Share on other sites
Looking for good contractors? Click here for your request

i'd think that delivery should be done last, electrical app first then furnitures

sequence should be something like this

1. re-tiling works

2. install air-con

3. install lights

4. painting

5. chemical wash

6. delivery of electrical app

7. delivery of furniture

hope it helps :bleah:

 

Share this post


Link to post
Share on other sites
hi, i will be doing some minor renovation to my resale flat. Below are the following things to be done :

1. re-tiling for the 2 toilets wall and floor + WC +toilet fixtures (done by reno contractor)

2.painting for the whole house (DIY)

3.dismantling and installation of new aircon sys3 in 3 bedrooms (aircon vendor)

4.installation of lights for the whole house (done by reno contractor)

5.delivery of electrical app like wm,fridge...etc

6.delivery of furnitures like sofa,table,bed+mattress

7.chemical wash for whole house (done by reno contractor)

Anyone can advice the sequence for the above mentioned?

Thanks a lot!

Since you are engagin a renovator, why not you check with your renovator so that there will not be any crash with his work. But Generally sequence is as follows subject to site condition:

a. All dismantling work first, including air con

b. Tiling work

c. Installation of Air Con

d. Painting to whole house

e. Chemical wash

f. Touch up paint

g. Delivery of electrical app and furniture last

 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×