I took up a reno package with 3D Innovations, signed the contract, paid the 10% deposit on 27th March 2016. Initial discussion & planning seems promising, however as time passes by, we noticed a pattern. On many occasions, there were tendencies to delay the jobs. Our timeline so far:
27th March 2016: Contract Signed & Paid 10% Deposit.
7th April 2016: Selection of Tiles etc.
13th April 2016: Meeting with our ID at their location at Sin Ming to confirm on our renovation specification, From this meeting our 3d drawing needs some changes so more time required.
27th April 2016: Site visit with our ID, to confirm what we have discussed earlier. Our ID said he will apply the HDB permit the next day & to commence the job once approve.
24th May 2016: HDB Issued permit for the partial hacking of our kitchen wall. We informed our ID about this approval, and We were surprised that he will request to HDB for extension... why the f*ck he needs extension for? Eventually the hacking job was done on 27th May 2016 after much pressure from our side, which initially he plan to do it the week after. We ask ID why it took so long (close to a month) for this permit, ID replied maybe due to overwhelming permit request to HDB.
30th May 2016: 40% cheque payment paid to ID as per their request in accordance to agreement. ID promised to make up for the time delay so far, and start the job(wet works) on that week.
3rd June 2016: Contacted ID to check how was the wet work progress, and calmly he said the tiles etc will only be delivered on next week (6th June 2016), and reno will start that week onwards.
Anyway this is just our initial experience with this company 3D Innovations. Hope things will improve once the Reno works flow in progress (which from our pattern analysis it is very unlikely )
So i believe my story is similar to BlessingMagnet555...
" You decide loh"