Four room new bto
1) Masonry work
Construct 50mm kitchen cabinet cement mortar base c/w side tiling
Construct 50mm fridge cement mortar base c/w full tilng
Construct 50mm washing machine cement mortar base c/w full tiling
2) Paint works
Painting of internal wall ( vinilex 5000)
Painting of all pipe with nippon gloss pain
3) Plumbing works
extension of stainless-steel piping for kitchen sink and washing machine
laying of drainage pipe for kitchen sink and washing machine
supply labour to install kitchen sink & tap
supply labour to install 2 set of instant heater
supply labour to install 2 set of bathroom accessories
4)Carpentry work
design & fabricate 20 ft kitchen cabinet in laminate finish c/w abs trimming swing door with stainless steel dish rack, using excel runner (laminate up to $58)
supply and install 10 ft solid surface worktop
supply labour to install cooker hood and hob
design and fabricate 6 ft full height wardrobe in laminate
5)Miscellaneous work
Floor protection with corrugated cardboard on affected area
general cleaning upon completion of works
Sub-Total: $8,088
To supply material and material to lay self-leveling in the following area :
living/dining - 660 ( $2 * 330 sqft)
masterbedroom - 292 ( $2 * 146 sqft)
bedroom 2 - 216 ($2 * 108 sqft)
bedroom 3 - 216 ($2 * 108 sqft)
To supply material and labour to lay 5mm vinyl flooring (HERF) w/o skirting in the following area
living/dining - 1815 ( $5 *363 sqft)
masterbedroom - 805 ( $5 * 146 sqft)
bedroom 2 - 595 ($2 * 108 sqft)
bedroom 3 - 595 ($2 * 108 sqft)
Sub total - $5334
Total 13422
Disc 222
After disc 13200