  1. Had some issues with the grout lines and had ID & PM to resolve before the carpentry is in this week. Had meeting with PM to verify the stuff completed last evening and notice the doors are installed. Looks good and to my liking... Doors for the rooms: http://i1372.photobucket.com/albums/ag351/lawda/WP_20140506_0071_zps29fe0970.jpg Door installed for the common toilet http://i1372.photobucket.com/albums/ag351/lawda/WP_20140506_0101_zpsbd4454ff.jpg
  2. Nothing was basically done over the weekend when i went back to check my unit but was kinda surprised during yesterday evening visit - lights are installed (not completed - outstanding LEDs and T5 lights). Took the opportunity to check out the tiles and marked out all issues i found for my ID to follow up before carpentry. Spent a good 2hrs yesterday to check and mark out the areas. Window grilles are all completed for the missing portion @ living, MBR and the access to a/c ledge. First coat of chosen paint are up and more to come..... Pictures to show on the progress Living room with different moods from the led lights (pending remaing leds and cove lightings) + completed grilles http://i1372.photobucket.com/albums/ag351/lawda/WP_20140429_0011_zps8607d4d6.jpg (cool blue) http://i1372.photobucket.com/albums/ag351/lawda/WP_20140429_0021_zps083a159a.jpg (warm white) http://i1372.photobucket.com/albums/ag351/lawda/WP_20140429_0031_zps83494593.jpg (day light) Cove light @ walkway http://i1372.photobucket.com/albums/ag351/lawda/WP_20140429_0041_zpsf5ea04a8.jpg Lighting in bedroom 1 & 2 http://i1372.photobucket.com/albums/ag351/lawda/WP_20140428_0011_zps7e668ed2.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140428_0021_zpsf9e665c9.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140428_0041_zps0bee6115.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140428_0071_zps7f136b58.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140428_0081_zpsc09c2836.jpg Outstanding grilles installed at MBR and a/c ledge http://i1372.photobucket.com/albums/ag351/lawda/WP_20140429_0051_zps075ada1c.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140429_0061_zpsf743d80f.jpg
  3. Was away for 10 days and didn't manage to liaise closely with ID on the carpentry design. However, ID did email me the design for the kitchen. As for bathroom 1, measurement and site visit has been done by carpentry. Will be providing my 3D design soon. Had long discussion with ID yesterday on paint selection and the carpentry design. Hope output will be great! Kitchen http://i1372.photobucket.com/albums/ag351/lawda/Blk315kitchen_zps4e80cc9d.jpg
  4. Thanks! i was surprised when i saw it this morning and whatapps my ID. he said he upgrade them to white to make the overall design look good.
  5. Got my 3D design this afternoon for MBR, bathroom2 and living room. Love it and it's up to our expectation. Can't wait for the revised kitchen and bathroom 1! Living Room http://i1372.photobucket.com/albums/ag351/lawda/Blk315living_zps8cf0161d.jpg MBR http://i1372.photobucket.com/albums/ag351/lawda/Blk315mainbedvw1_zps0eb4e5bf.jpg http://i1372.photobucket.com/albums/ag351/lawda/Blk315mainbedvw2_zps3a35cac7.jpg http://i1372.photobucket.com/albums/ag351/lawda/Blk315mainbedvw3_zps1c3f8d80.jpg Bathroom2 http://i1372.photobucket.com/albums/ag351/lawda/Blk315bath2_zps5a907f0c.jpg
  6. Had city gas came to install the pipe. It was job well done by the friendly uncle within a short span of time. Pipe are tucked as close to the wall and corner marked by ID. Some pictures of the installation: http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_014_zpse442a0c1.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_017_zps28a7cd67.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_018_zps1375633e.jpg Some update on the progress for the week: Tiles are almost completed with only skirting left to be done living room; http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_034_zps82e30564.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_033_zps7ded7d75.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_030_zps46f9cac8.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_029_zps9e1a09c7.jpg Kitchen cabinets' bases are almost done too: http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_020_zps694b4320.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_019_zpsd0c51321.jpg ID gave me a surprise with his good gesture and taste. He actually upgraded my plain original colour aluminium grille to white coloured powered (slightly costly) just to ensure the overall design looks good http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_008_zps0c4c9138.jpg Window grilles are up for most of the rooms, living and yard http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_022_zpsf6590d5a.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_026_zps7f750522.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_031_zps6778c030.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_013_zpsd40a79c9.jpg Slope at main gate demolished for tiling http://i1372.photobucket.com/albums/ag351/lawda/WP_20140412_024_zpsb9a821bf.jpg
  7. Update on the ceiling works and tiling done last week: Ceiling works at the 2 rooms: http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_006_zps78a9c714.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_009_zpsd44de1e5.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_008_zps53ca58cd.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_005_zps93152312.jpg Ceiling works at MBR http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_012_zpsefa69233.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_011_zps278187ba.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_010_zps8d765eee.jpg Ceiling work at Walkway to rooms http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_007_zps479338be.jpg Ceiling works Living/Dining http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_018_zpsba1fb7fe.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_015_zps28d58157.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_014_zpsee358e29.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140405_013_zps6988e407.jpg Tiling works completed last week (in progress) http://i1372.photobucket.com/albums/ag351/lawda/WP_20140407_007_zps2db67f75.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140407_006_zps9786956a.jpg
  8. 3D design not yet finalised but we had the location of the aircon fixed and installed. "unfortunately", we engaged the "famous" provider in this forum without reading through the negative feedback. We pressed on with communication with the sales person and service manager and things work out well. My post on my experience as follows: http://www.renotalk.com/forum/topic/14091-best-tech-aircon-imm/page-3#entry848049 some pictures of my installation done 2 weeks back. Agreed and offered insulation during the purchase from sales http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_012_zps57f2abf1.jpg Thick trunking used, may look horrible for some but to me its one trunk instead of 2 trunks running http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_008_zps8f96d12e.jpg installer does put in good point, he actually runs the full trunking length across the wall even though there's no need to as the pipe is at the middle of the wall. Reason, 3/4 trunk running across the wall will be very obvious. Full length and after painting is done, the trunk will look less obvious and blend in with the beam. http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_007_zpsd48d6fac.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_006_zps47fb14d2.jpg To ease my fear of condensation and leaking pipe, installer advise to shorten the route for water to be drained. Simple law of physics which we returned to the teachers in search of aesthetics... http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_005_zpsc6d344d3.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_001_zps3d217367.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140329_002_zps0f564921.jpg Location of my Units http://i1372.photobucket.com/albums/ag351/lawda/WP_20140328_014_zps2c03b3e0.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140328_016_zps31eeea23.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140328_017_zps94e0ee9c.jpg http://i1372.photobucket.com/albums/ag351/lawda/WP_20140328_018_zpsa94b77fa.jpg
  9. Got my key in February 2014 and appointed my ID in March. Been through few reviews, quotes and visiting real sites of potential IDs workmanship before we conclude on the one recommended in this forum. It's my first posting with image and hope the standard unit plan from HDB works.....
  10. lawda

    New begining

  11. lawda

    Unit Layout

    From the album: New begining

  12. i got my ID/contractor to customise one for me with storage. Cost $1.2k, not sure if its exp
×