A. Demolition Works
1. Hacking of existing floor tiles for kitchen --- 350
2. Hacking of existing floor and wall tiles for Master Toilet --- 300
3. Hacking of existing floor and wall tiles for Common Toilet --- 300
4. hacking of existing existing concrete base for sink/stove support at kitchen --- 150
5. Hacking of toilet bowls, basins and basin concrete supports --- 80
6. Hacking of existing wall between Master Bedroom and Bedroom 2 --- 280
7. Dismantle and dispose existing Kitchen Cabinets --- 180
8. Dismantle and dispose existing Wardrobe, Bedframe and Bedhead in Master Bedroom --- 200
9. Dismantle and dispose existing L-boxes in Living/Dining and Master Bedroom --- 200
10. Dismantle and dispose existing doors at Kitchen Entrance, Master Toilet entrance and Common toilet entrance --- 80
11. Hacking of wall between living hall and common bedroom & make good wall --- 260
12. Dismantle and dispose existing L-boxes in Bedroom 2 --- 120
B. Masonry Works
1. Supply and lay ceramic/homogeneous floor tiles for Kitchen (range of tiles $3psf) --- 880
2. Supply and construct non-slip ceramic/homogeneous floor and wall tiles for master Toilet (range of tiles $3psf) --- 1400
3. Supply and construct non-slip ceramic/homogeneous floor and wall tiles for common toilet (range of tiles $3psf) --- 1400
4. Supply and construct shower kerb for master toilet --- 90
5. Supply and construct shower kerb for common toilet --- 90
6. Apply waterproofing membrane for master toilet --- 120
7. Apply water proofing membrane for common toilet --- 120
8. Apply water proofing membrane for kitchen --- 150
9. Supply and construct new wall between Master Bedroom and Common Bedroom at Proposed new location --- 980
10. Plaster smooth existing wall tiles at kitchen --- 650
11. To make good affected area after demolition of existing wall --- 180
12. Replace 15pcs of granite floor (include hacking) --- 1080
13. Supply and install granite skirting --- 150
C. Ceiling and Partition Works
1. Supply and install plasterboard false ceiling and cove light box at foyer/living & dining as discussed --- 980
2. Supply and install plasterboard flase ceiling and cove light box at master Bedroom --- 630
D. Plumbing Works
1. Supply and replace whole house piping to stainless steel (hot/cold pipe for 2 toilets) --- 650
2. Supply and replace new stainless steel piping for washing machine --- 50
3. Supply and replace new conceal drain pipe for washing machine --- 50
4. Supply and replace new stainless steel piping for sink --- 50
5. Supply and replace new conceal drain pipe for sink --- 50
6. Supply labour to install new kitchen sink and tap --- 60
7. Supply labour to intall all basins and tap --- 120
8. Supply labour to install all toilet bowls --- 160
9. Supply labour to install all toilet accessories --- 40
E. Doors/Glass/Windows
1. Supply and install timber door frame at new proposed Master Bedroom --- 150
2. Labour to remove and reinstall existing door for master bedroom --- 60
3. Supply and install 10mm tempered glass shower screen at master toilet c/w hand rail & towel rail ---380
4. Supply and install 10mm tempered glass shower screen at common toilet c/w hand rail & towel rail --- 380
5. Supply and install acrylic bi-fold door at common toilet --- 200
F. Carpentry Works
1. Foyer: Full height feature wall with Tic-Tac door & shoe cabinet to cover HHS door in laminate finish (7ft) --- 1400
2. Living: Half height TV feature wall in laminate finish (8ft) --- 830
3. Living: Suspended TV console in laminate finish (6ft) --- 720
4. New Dining: Construct full height feature wall with 2 strips of horizontal mirror in laminate finish (13ft) --- 2880
5. New Dining: Construct L-shaped settee with storage (13ft) --- 1500
6. New Study Area: Construct suspended working table (9ft) --- 590
7. Kitchen: Top & bottom solid plywood cabinet in laminate & ABS trimmins finished c/w anti slam soft closing hinges. 1pc aluminium framed frosted glass door, stainless steel dish rack and cutlery tray (35ft) --- 3750
8. Kitchen: L-shape solid surface top for cabinet (15ft) --- 970
9. Kitchen: Labur to install cooker hob & hood --- 40
10. Master Bedroom: Construct partition wall to create walk-in wardrobe (15ft) --- 680
11. Master Bedroom: Construct frosted glass door for walk-in wardrobe --- 400
12. Master Bedroom: Construct walk-in wardrobe in color pvc --- 2090
G. Whole House and Generals
1. Painting of whole house walls/ceilings with Nippon Paint (5 color + 1 white for ceiling) --- 900
2. painting of all pipings, bedroom doors/frames and varnish main door --- 250
3. Supply and lay corrogated board to protect existing granite flooring (incude disposal) --- 150
4. Debris removal --- 300
5. haulage fee --- 350
6. Acid wash and general cleaning --- 180
H. Electrical Works
1. Add/shift 1 no. socket power outlet --- 45
2. Add/shift 1 no. double socket power outlet --- 55
3. Add 1 no. oven point --- 90
4. Add 1 no of light point/cooker hood point --- 35
5. Install 1 no. ceiling/false ceiling light/cove lighting --- 10
6. Add/shift 1 no SCV point --- 120
7. Add/shift 1 no tel point --- 45
GRAND Total of $32,530. Mine is a 4A HDB resale flat, 92 sqm.