Up till now, the sequence is like this:
- Demo (9 Sept, 13 Sept)
- Clearing (14 Sept)
- Upload materials (14 Sept)
- Tiling bath/WC floor, kitchen wall, install door frame (15 Sept)
- Tiling living room/bedrooms, grouting, cementing door frame (16 Sept, 17 Sept)
- Rework tiling living room/kitchen, gas-meter relocation, grouting, touchup (18 Sept, 20 Sept)
- Delivery of sink, taps, etc (21 Sept)
- AC rewiring (22 Sept, 16 Oct)
- Windows (23 Sept)
- Plumbing/aircon piping & condenser installation (24 Sept)
- Ceiling works (28 Sept, 29 Sept)
- Painting works (01 Oct, 02 Oct)
- Installation of aircon FCU (02 Oct)
- Lighting and switches installation (05 Oct)
- Acid cleaning and touchup (06 Oct)
- Carpentry (07 Oct, 13 Oct, 16 Oct)
- Glassworks (07 Oct, 12 Oct)
- OpenNet installation (13 Oct)
- Installation of window grilles (13 Oct)
- Installation of doors (13 Oct)
- Handover (30 Oct)