Blog Entry Date: 11th October 2017 Wednesday Click Here to go back to Page 1 - Table of Contents 4th week after Key Collection. Tiling completed, Important Milestone reached.
A Prepping Week for the next Milestone
With Tiling completed, an important milestone has concluded and now 4th Week begins.
From what I understand from Jason, the action plan for this week is:
1) Early week, Electrical guys come up to settle any power points that are still outstanding.
2) Clearing of Rubbish and Removal of Bulky Trash to be done midweek on Wednesday and Thursday
3) Jason setting up appointment with his Carpenter for discussion on next Carpentry Milestone
4) Painters to come at end of the week Next Monday to start Painting Works after all Rubbish has been removed.
5) Meeting Jason on Saturday to go buy my Kitchen/Bathroom Stuffs, Appointment with Carpenter for Carpentry Discussions
As you can see, there isn't much action for 4th week, its more like a Prepping Week to Prepare
for the Next Major Milestone which is Painting / Carpentry / Lightings.
----------------------------------------------------------
Below are the pictures I've just captured of most of the rubbish cleared, and a better picture of
how the finished tiling works looks like. What do ya'll think of the workmanship? (Warning: Massive amount of Pictures ahead)
---------------------------------------------------------- Bathroom Pictures of the Bathroom taken from outside: Bathroom Floor (Notice the difference in height? Left side closer to entrance is Dry Area, right side shower area is Wet Area.
There will be a glass panel put in later to divide the 2 areas. Close up of the Bathroom Floor Bathroom Ceiling Corner Another Bathroom Ceiling Corner Side of the Bathroom Wall showing the Aircon Trunking
---------------------------------------------------------- Kitchen I have shown this before, but here it is again.
This is the side of Kitchen Wall thats facing the Main Door. Overall look of tiling and kerbs completed in Kitchen. Kerb at the Washing Machine and Kitchen Sink side
(Left side is Washing Machine, Right side is Kitchen Sink) Close up look of the Kitchen Sink Kerb Close Up look of the Washing Machine Kerb View of the Kerb on the other side of the Kitchen where my Oven, Induction Stovetop, Refridgerator are located Close up look of the Refridgeratror Kerb Close up look at the Induction Stovetop, Oven side Kerb Another overall look at the completed tiling work in the Kitchen
(This time also including the Laundry Rack)
---------------------------------------------------------- Living Room
Different Views of my Living Room Ceiling L-Box Cove Lighting
Do you remember previously in the Living Room after both Sliding Door and False wall
were removed, there was a massive big gaping hole that looks like this?
Well, this hole has also been patched up very nicely using the spare tiles given by HDB as shown below.
Other than a bit of touchup on the Wooden Skirting, you will never know there used to be a big hole there.
So many pictures of the completed work. How do you find the workmanship?
Anyway this concludes my report for the 4th week.
I am very happy that an important milestone has been completed mostly without hitches and on schedule.
Thanks for visiting, I'll see you in the next Blog Entry! Click Here for the Next Blog Entry: My Mid-Renovation Review of my Interior Designer Click Here to go back to Page 1 - Table of Contents